Stage 3a - Pre-application
You can click through these bubbles to navigate to each Stage.
This stage is optional, as it is not a requirement of the National Electricity Rules (NER).
After completing Stage 2 – Enquiry and receiving an Enquiry Response Victorian Planning & Connections (VP&C) a Pre-application stage.
Pre-application provides more detailed analysis for your proposed connection, greater understanding of the overall application process and early engagement and planning of your project with VP&C stakeholders and any early assistance with modelling requirements, if required.
In the Pre-application stage, we assign a dedicated Project Manager who will put together a team of internal experts to assist with the scope of works you are interested in engaging us in.
Pre-application includes six scope items you can choose that we will work on with you. Below are a list of the items, for further details on the scope items refer to thePre-application form.
Scope Item |
Scope Topic |
---|---|
1 |
Project Program |
2 |
Provision of Location Specific Critical Network Information |
3 |
Location Specific Constraints and Project Scope Assessment |
4 |
Infrastructure and Contracts |
5 |
System models and performance standards |
6 |
Preliminary model tuning assessments |
To request Pre-application services, please submit a Connection Pre-application Form and any supporting information to us.