Market Notices

118426MARKET INTERVENTION24/09/2024 04:00:14 PM

Direction - SA region 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 24/09/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 24/09/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
118425MARKET INTERVENTION24/09/2024 03:58:46 PM

Direction - SA region 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 24/09/2024

Refer to Market Notice 118426


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 24/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 1000 hrs 25/09/2024
Services provided: Voltage Control
Circumstances necessitating the Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state

Expected duration: 0400 hrs 26/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118424MARKET INTERVENTION24/09/2024 03:57:30 PM

Direction - SA region 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 24/09/2024


Refer to Market Notice 118426


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 24/09/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 1000 hrs 25/09/2024
Services provided: Voltage Control
Circumstances necessitating the Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state

Expected duration: 0400 hrs 26/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118423MARKET INTERVENTION24/09/2024 03:00:55 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118419

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1000 hrs 25/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 24/09/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
118419MARKET INTERVENTION24/09/2024 12:57:47 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1000 hrs 25/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
118416MARKET SYSTEMS24/09/2024 10:24:04 AM

CHG0098666:Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098666
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600




     
118415MARKET SYSTEMS24/09/2024 10:22:22 AM

CHG0098678:Telstra Melbourne Indial (03 9609 XXXX-XXXX)

Change Number: CHG0098678
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cisco IP Phone
Change Title: Telco Outage Notification - Telstra Melbourne Indial (03 9609 XXXX-XXXX)
Change Start Date & Time: 08/10/2024 00:00:00 AEST
Change End Date & Time: 08/10/2024 06:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: Outage Duration:
3 x 15 Minutes during the window

Impacts:
Reduced redundancy for Inbound and Outbound Calls (automatically rerouted via Perth).
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
118413NON-CONFORMANCE24/09/2024 09:50:12 AM

NON-CONFORMANCE Region QLD1 Tuesday, 24 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 24 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KSP1
Duration: 24/09/2024 09:20 to 24/09/2024 09:50
Amount: 48 MW
Constraint: NC-Q_KSP1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118408MARKET INTERVENTION23/09/2024 04:01:30 PM

Cancellation - Foreseeable intervention to manage power system security in SA region 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Foreseeable intervention to manage power system security in SA region 24/09/2024

Refer Market Notice 118400

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1600 hrs 23/09/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm