118400MARKET INTERVENTION23/09/2024 01:13:51 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0000 hrs 24/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
118398RECLASSIFY CONTINGENCY23/09/2024 12:53:03 PM

Cancellation - Reclassification of a Non-Credible Contingency Event: Eraring Power Station in NSW Region 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Reclassification of a Non-Credible Contingency Event: Eraring Power Station in NSW Region 23/09/2024

Refer to MN 118393

Based on advice from the asset owner, AEMO no longer considers the simultaneous trip of Eraring Power Station Units 2 and 4 as a credible contingency event.


Therefore AEMO cancels the reclassification as a credible contingency event from 1250 hrs 23/09/2024.

Constraint set N-ERARING_N-2 revoked from 1250 hrs 23/09/2024

Manager NEM Real Time Operations
     
118397MARKET INTERVENTION23/09/2024 12:46:38 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Participant Notice 118372

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 23/09/2024.

The direction update is issued at 1240 hrs 23/09/2024.

Manager NEM Real Time Operations
     
118393RECLASSIFY CONTINGENCY23/09/2024 09:50:10 AM

Reclassification of a Non-Credible Contingency Event: Eraring Power Station in NSW Region 23/09/2024

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event: Eraring Power Station in NSW Region 23/09/2024

Based on advice from the asset owner, AEMO has declared the simultaneous trip of Eraring Power Station Units 2 and 4 as a credible contingency event.

AEMO considers the simultaneous trip of those generators to now be more likely.

AEMO has reclassified this as a credible contingency event from 1000 hrs 23/09/2024.

To manage power system security constraint set N-ERARING_N-2 invoked from 1000 hrs 23/09/2024 until further notice.

Manager NEM Real Time Operations
     
118389NON-CONFORMANCE23/09/2024 05:45:14 AM

NON-CONFORMANCE Region QLD1 Monday, 23 September 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 23 September 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: W/HOE#2
Duration: 23/09/2024 05:30 to 23/09/2024 05:45
Amount: -165 MW
Constraint: NC-Q_W/HOE#2

Auto-generated on behalf of Manager NEM Real Time Operations
     
118379MARKET INTERVENTION23/09/2024 03:59:18 AM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 118386

Direction is cancelled from: 0400 hrs 23/09/2024

Manager NEM Real Time Operations
     
118378MARKET INTERVENTION23/09/2024 04:00:34 AM

Cancellation - AEMO Intervention Event - SA region 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 22/09/2024

Refer to Market Notice 118376

The AEMO Intervention Event and all associated directions are cancelled from 0400 hrs on 23/09/2024.



Manager NEM Real Time Operations
     
118376MARKET INTERVENTION22/09/2024 07:06:53 PM

Direction - SA region 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 22/09/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1855 hrs on 22/09/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
118375MARKET INTERVENTION22/09/2024 06:50:12 PM

Direction - SA region 22/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 22/09/2024



In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1850 hrs 22/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 1850 hrs 22/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1950 hrs 22/09/2024.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     