Filter by category
Filter by Date
[EventId:202505131830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 May 2025 18:30
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 13 May 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 May 2025.
Refer to market notice: 127032
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 13 May 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202505131635_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 May 2025 16:35
Issued by Australian Energy Market Operator Ltd at 1635 hrs on 13 May 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 May 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1635 hrs on 13 May 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202505131545_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 13 May 2025 15:45
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 13 May 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 May 2025.
Refer to market notice: 127024
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1545 hrs on 13 May 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202505131500_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 13 May 2025 15:00
Issued by Australian Energy Market Operator Ltd at 1500 hrs on 13 May 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 13 May 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1500 hrs on 13 May 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
NON-CONFORMANCE Region NSW1 Monday, 12 May 2025
NON-CONFORMANCE NSW1 Region Monday, 12 May 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 12/05/2025 15:05 to 12/05/2025 15:10
Amount: -9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Sunday, 11 May 2025
NON-CONFORMANCE VIC1 Region Sunday, 11 May 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: COHUNSF1
Duration: 11/05/2025 12:00 to 11/05/2025 12:15
Amount: 17 MW
Constraint: NC-V_COHUNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 9 May 2025
NON-CONFORMANCE NSW1 Region Friday, 9 May 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: NYNGAN1
Duration: 09/05/2025 09:55 to 09/05/2025 10:20
Amount: -85 MW
Constraint: NC-N_NYNGAN1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 9 May 2025
NON-CONFORMANCE NSW1 Region Friday, 9 May 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WOLARSF1
Duration: 09/05/2025 09:40 to 09/05/2025 09:50
Amount: 11 MW
Constraint: NC-N_WOLARSF1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202505071930_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 07 May 2025 19:30
Issued by Australian Energy Market Operator Ltd at 1930 hrs on 7 May 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 7 May 2025.
Refer to market notice: 126940
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1930 hrs on 7 May 2025.
This is an AEMO autogenerated Market Notice.