Market Notices

118426MARKET INTERVENTION24/09/2024 04:00:14 PM

Direction - SA region 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 24/09/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 24/09/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
118425MARKET INTERVENTION24/09/2024 03:58:46 PM

Direction - SA region 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 24/09/2024

Refer to Market Notice 118426


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 24/09/2024
Type of resource: generating unit
Required actions: remain synchronised and follow dispatch targets at 1000 hrs 25/09/2024
Services provided: Voltage Control
Circumstances necessitating the Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state

Expected duration: 0400 hrs 26/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118424MARKET INTERVENTION24/09/2024 03:57:30 PM

Direction - SA region 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 24/09/2024


Refer to Market Notice 118426


In accordance with clause 4.8.9(a)(1) of the National Electricity Rules, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1600 hrs 24/09/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 1000 hrs 25/09/2024
Services provided: Voltage Control
Circumstances necessitating the Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state

Expected duration: 0400 hrs 26/09/2024.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
118423MARKET INTERVENTION24/09/2024 03:00:55 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118419

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1000 hrs 25/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 24/09/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
118421MINIMUM SYSTEM LOAD24/09/2024 02:54:54 PM

Minimum System Load 1 (MSL1) in the VIC Region on 28/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs to 1400 hrs 28/09/2024.
Minimum regional demand is forecast to be 1638 MW at 1300 hrs, and the advisory threshold is:
- MSL1 - 1865 MW
- MSL2 - 1365 MW
- MSL3 - 865 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold.

Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

AEMO is seeking a market response.

An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

AEMO Operations
     
118419MARKET INTERVENTION24/09/2024 12:57:47 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1000 hrs 25/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
118414RESERVE NOTICE24/09/2024 10:14:24 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118412 is cancelled at 1015 hrs 24/09/2024.

Manager NEM Real Time Operations
     
118412RESERVE NOTICE24/09/2024 09:38:00 AM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:

From 1900 hrs 24/09/2024 to 2000 hrs 24/09/2024.
The forecast capacity reserve requirement is 350 MW.
The minimum capacity reserve available is 311 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
     
118410RESERVE NOTICE23/09/2024 10:26:36 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 24/09/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 118409 is cancelled at 2215 hrs 23/09/2024.

Manager NEM Real Time Operations
     