Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024
Inter-regional transfer limit variation - Keilor to Sth Morang 500kV Line - VIC region - 04/08/2024
A planned outage of Keilor to Sth Morang 500kV Line in the VIC region was scheduled from 1000 hrs 04/08/2024 to 1300 hrs 04/08/2024.
The outage has been completed and Keilor to Sth Morang 500kV Line returned to service at 1050 hrs 04/08/2024
Constraint set(s) revoked: V-KTSM_R
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 4 August 2024
NON-CONFORMANCE QLD1 Region Sunday, 4 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: W/HOE#2
Duration: 04/08/2024 06:25 to 04/08/2024 06:30
Amount: -165 MW
Constraint: NC-Q_W/HOE#2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 3 August 2024
NON-CONFORMANCE NSW1 Region Saturday, 3 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW03
Duration: 03/08/2024 16:25 to 03/08/2024 16:35
Amount: 72 MW
Constraint: NC-N_BW03
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Friday, 2 August 2024
NON-CONFORMANCE SA1 Region Friday, 2 August 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 02/08/2024 12:10 to 02/08/2024 18:15
Amount: 14 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Thursday, 1 August 2024
NON-CONFORMANCE SA1 Region Thursday, 1 August 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 01/08/2024 13:55 to 01/08/2024 17:35
Amount: 28 MW
Constraint: NC-S_TB2HYB_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Thursday, 1 August 2024
NON-CONFORMANCE VIC1 Region Thursday, 1 August 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS4
Duration: 01/08/2024 06:50 to 01/08/2024 06:55
Amount: 24 MW
Constraint: NC-V_YWPS4
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Wednesday, 31 July 2024
NON-CONFORMANCE NSW1 Region Wednesday, 31 July 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW01
Duration: 31/07/2024 13:30 to 31/07/2024 13:35
Amount: -17 MW
Constraint: NC-N_BW01
Auto-generated on behalf of Manager NEM Real Time Operations
Increase to QNI limit to next hold point of 1400 MW Qld to NSW
Refer to market notices 117060.
AEMO, TransGrid, Powerlink have reviewed the test results following the QNI minor testing on 19th June 2024. The next hold point can now be released.
The hold point of 1400 MW from Qld to NSW will be implemented as of 1000 hrs 31st July 2024.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Inter-regional transfer limit variation - Heywood - South East No 2 275 kV Line - SA region - 26/07/2024
Inter-regional transfer limit variation -Heywood - South East No 2 275 kV Line SA region - 26/07/2024
A planned outage of Heywood - South East No 2 275 kV Line in the SA region was scheduled from 0830 hrs 26/07/2024 to 1730 hrs 28/07/2024.
The outage has been extended until 1200 hrs 29/07/2024
Constraint set(s) invoked:
I-HYSE
I-VS_050
I-VS+LKB_050
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations