66831RECLASSIFY CONTINGENCY25/01/2019 05:02:05 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 25/01/2019 17:02 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
66830PRICES UNCHANGED25/01/2019 04:09:31 PM

[EventId:201901241750_confirmed] Prices for interval 24-Jan-2019 17:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1609 hrs on 25 January 2019

PRICES ARE NOW CONFIRMED for dispatch interval 24-Jan-2019 17:50.

In accordance with Market Notice 66658 AEMO has reviewed this dispatch interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
66829RECLASSIFY CONTINGENCY25/01/2019 04:12:36 PM

Reclassification of a Non-Credible Contingency Event:Palmerston - Liapootah - Waddamana - Palmerston No. 1 and No. 2 220 kV Lines and the Palmerston - Waddamana 110kV line in Tasmania due to bushfire

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a Non-Credible Contingency Event: Liapootah - Waddaman - Palmerston No. 1 and No. 2 220 kV Lines in Tasmania due to bushfire.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS

Lines: Liapootah - Waddamana - Palmerston No. 1 and No. 2 220 kV Lines and the Palmerston - Waddamana 110kV line

Duration: 25/01/2019 1610 hrs until further notice
Constraint set(s) invoked: T-LIPM_PMWA_N-3

Manager NEM Real Time Operations
66828RESERVE NOTICE25/01/2019 04:01:03 PM

Cancellation of Actual (LOR2) condition in the Vic region - 25/01/2019

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR2 Condition in the Vic Region advised in AEMO Electricity Market Notice No.66751 is cancelled at 1600 hrs 25/01/2019.

Manager NEM Real Time Operations
66827MARKET INTERVENTION25/01/2019 04:30:43 PM

Cancellation - AEMO Intervention Event -Intervention price dispatch intervals

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention price dispatch intervals
Refer Market Notice 66822.
The AEMO Intervention Event, the dispatch of Reliability and Emergency Reserve Trader (RERT) has ended at 1630 hrs 25/01/2019. Activation of reserve contract(s) for RERT dispatch in VIC1 has ended.

Manager NEM Real Time Operations
66826PRICE ADJUSTMENT25/01/2019 03:30:16 PM

[EventId:201901241700_confirmed] Prices for interval 24-Jan-2019 17:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1530 hrs on 25 January 2019

PRICES ARE NOW CONFIRMED for dispatch interval 24-Jan-2019 17:00.

In accordance with Market Notice 66636 AEMO has reviewed this dispatch interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
SA1 $9,666.67 $13,654.72


This is an AEMO autogenerated Market Notice.
66825PRICE ADJUSTMENT25/01/2019 03:29:02 PM

[EventId:201901241655_confirmed] Prices for interval 24-Jan-2019 16:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1529 hrs on 25 January 2019

PRICES ARE NOW CONFIRMED for dispatch interval 24-Jan-2019 16:55.

In accordance with Market Notice 66635 AEMO has reviewed this dispatch interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Changed Prices ($/MWh)

TYPE
Region Original Adjusted
Price Price
ENERGY
VIC1 $9,666.67 $13,777.63


This is an AEMO autogenerated Market Notice.
66824PRICES UNCHANGED25/01/2019 03:26:07 PM

[EventId:201901241640_confirmed] Prices for interval 24-Jan-2019 16:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1526 hrs on 25 January 2019

PRICES ARE NOW CONFIRMED for dispatch interval 24-Jan-2019 16:40.

In accordance with Market Notice 66632 AEMO has reviewed this dispatch interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
66823SETTLEMENTS RESIDUE25/01/2019 02:50:15 PM

[EventId:201901251450_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 25 January 2019 14:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1450 hrs on 25 January 2019

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 25 January 2019.

Refer to market notice: 66810

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1450 hrs on 25 January 2019.

This is an AEMO autogenerated Market Notice.