127330GENERAL NOTICE29/05/2025 02:42:44 PM

Fast Frequency Response Market - Local dispatch of Very Fast Contingency FCAS in SA and QLD

AEMO ELECTRICITY MARKET NOTICE

Following a review of the operation of the Very Fast FCAS market, AEMO will commence local dispatch of Very Fast FCAS in the South Australia (SA) and Queensland (QLD) regions from 10th June 2025, during periods where islanding of the region is considered credible.

An initial dispatch cap of 100 MW will apply in the SA region, and 20 MW in the QLD region. These caps will be reviewed and updated regularly.

From the same date, AEMO will also dispatch Very Fast FCAS in the QLD region when an actual islanding event occurs. In this scenario, no dispatch cap will apply.

Dispatch of Very Fast FCAS in the SA region under actual islanding conditions commenced in 2024. Refer to Market Notice 117238 for further details.

For more information on the Fast Frequency Response (FFR) initiative, please visit:
https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Andrew Groom
AEMO Operations
     
127008RESERVE NOTICE12/05/2025 08:39:09 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127006 is cancelled at 2035 hrs 12/05/2025

AEMO Operations
     
127006RESERVE NOTICE12/05/2025 05:12:44 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127003 has been updated at 1600 hrs 12/05/2025 to the following:

1. From 1130 hrs to 1200 hrs 15/05/2025.
The forecast capacity reserve requirement is 459 MW.
The minimum capacity reserve available is 457 MW.

2. From 1430 hrs to 1530 hrs 15/05/2025.
The forecast capacity reserve requirement is 467 MW.
The minimum capacity reserve available is 456 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127003RESERVE NOTICE12/05/2025 04:00:44 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 126998 has been updated at 1500 hrs 12/05/2025 to the following:

From 1430 hrs to 1500 hrs 15/05/2025.
The forecast capacity reserve requirement is 461 MW.
The minimum capacity reserve available is 453 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
126998RESERVE NOTICE12/05/2025 02:03:00 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1030 hrs to 1230 hrs 15/05/2025.
The forecast capacity reserve requirement is 438 MW.
The minimum capacity reserve available is 401 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
126784GENERAL NOTICE20/05/2025 06:03:57 PM

Network Augmentation Commissioned - NSW Region - 20/05/2025

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - NSW Region - 20/05/2025

At 1700 hrs 20/05/2025, the Buronga No.5 330kV synchronous condenser has been commissioned.

Manager NEM Real Time Operations
     
126771GENERAL NOTICE29/04/2025 08:40:07 PM

Network Augmentation Commissioned - Vic Region - 29/04/2025

AEMO ELECTRICITY MARKET NOTICE


Network Augmentation Commissioned - Vic Region - 29/04/2025

At 2030hrs 29/04/2025, the existing Haunted Gully - Tarrone No1 500 kV transmission line has been cut in at Mortlake Power Station to create the following transmission line sections:

Mortlake PS - Tarrone No.1 500 kV transmission line
Mortlake PS - Haunted Gully No.1 500 kV transmission line

Manager NEM Real Time Operations
     
126722GENERAL NOTICE24/04/2025 03:59:43 PM

Release of QNI limit from NSW to Qld - 29th April 2025

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 124749.

AEMO, Transgrid, Powerlink have reviewed the test results following the QNI minor testing on 16th February 2025. The next hold point can now be released.

The hold point of 950 MW from NSW to Qld will be implemented as of 1000 hrs 29th April 2025.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
     
126560RESERVE NOTICE14/04/2025 06:13:59 PM

Cancellation of Actual (LOR1) condition in the NSW region - 14/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 14/04/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.126559 is cancelled at 1811 hrs 14/04/2025.