127222RECLASSIFY CONTINGENCY25/05/2025 03:04:30 AM

Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Duration: 25/05/2025 03:04 until further notice

Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
     
127221RECLASSIFY CONTINGENCY25/05/2025 03:00:05 AM

Reclassification of a Non-Credible Contingency Event: Norwood - Scottsdale 1 110kV line and Norwood-Derby-Scottsdale 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Norwood - Scottsdale 1 110kV and Norwood-Derby-Scottsdale 110kV

Duration: 25/05/2025 03:00 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
127220RECLASSIFY CONTINGENCY25/05/2025 02:38:40 AM

Reclassification of a Non-Credible Contingency Event: George Town - Sheffield 1&2 220kV + Nyrstar&Temco line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: George Town - Sheffield 1&2 220kV + Nyrstar&Temco and

Duration: 25/05/2025 02:35 until further notice

Constraint set(s) invoked:
T-GTSH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
     
127219RECLASSIFY CONTINGENCY25/05/2025 02:35:16 AM

Reclassification of a Non-Credible Contingency Event: Ulverstone - Emu Bay 110kV line and Sheffield - Paloona - Ulverstone 1 & 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Ulverstone - Emu Bay 110kV and Sheffield - Paloona - Ulverstone 1 & 2 110kV

Duration: 25/05/2025 02:35 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
127218RECLASSIFY CONTINGENCY25/05/2025 02:23:01 AM

Reclassification of a Non-Credible Contingency Event: Burnie - Port Latta - Smithton 1 110kV line and Burnie - Port Latta - Smithton 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Burnie - Port Latta - Smithton 1 110kV and Burnie - Port Latta - Smithton 2 110kV

Duration: 25/05/2025 02:22 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
127217RECLASSIFY CONTINGENCY25/05/2025 02:09:00 AM

Cancellation of a Non-Credible Contingency Event: Ulverstone - Emu Bay 110kV line and Sheffield - Paloona - Ulverstone 1 & 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Ulverstone - Emu Bay 110kV and Sheffield - Paloona - Ulverstone 1 & 2 110kV

Cancellation time: 25/05/2025 02:08

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 127214

Auto-generated on behalf of Manager NEM Real Time Operations
     
127216RECLASSIFY CONTINGENCY25/05/2025 02:08:56 AM

Cancellation of a Non-Credible Contingency Event: George Town - Sheffield 1&2 220kV + Nyrstar&Temco line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: George Town - Sheffield 1&2 220kV + Nyrstar&Temco and

Cancellation time: 25/05/2025 02:08

Constraint set(s) revoked:
T-GTSH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Refer AEMO Electricity Market Notice 127215

Auto-generated on behalf of Manager NEM Real Time Operations
     
127215RECLASSIFY CONTINGENCY25/05/2025 01:07:47 AM

Reclassification of a Non-Credible Contingency Event: George Town - Sheffield 1&2 220kV + Nyrstar&Temco line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: George Town - Sheffield 1&2 220kV + Nyrstar&Temco and

Duration: 25/05/2025 01:07 until further notice

Constraint set(s) invoked:
T-GTSH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
     
127214RECLASSIFY CONTINGENCY25/05/2025 01:07:46 AM

Reclassification of a Non-Credible Contingency Event: Ulverstone - Emu Bay 110kV line and Sheffield - Paloona - Ulverstone 1 & 2 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Ulverstone - Emu Bay 110kV and Sheffield - Paloona - Ulverstone 1 & 2 110kV

Duration: 25/05/2025 01:07 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     