Market Notices

127404NON-CONFORMANCE05/06/2025 08:10:13 PM

NON-CONFORMANCE Region QLD1 Thursday, 5 June 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 5 June 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 05/06/2025 19:30 to 05/06/2025 20:10
Amount: 23 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
127402RESERVE NOTICE05/06/2025 02:43:05 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 12/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 1800 hrs to 1830 hrs 12/06/2025.
The forecast capacity reserve requirement is 1618 MW.
The minimum capacity reserve available is 1595 MW.

AEMO Operations
     
127401RESERVE NOTICE05/06/2025 02:43:04 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 10/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 1730 hrs to 1830 hrs 10/06/2025.
The forecast capacity reserve requirement is 1502 MW.
The minimum capacity reserve available is 1301 MW.

AEMO Operations
     
127399RESERVE NOTICE05/06/2025 11:22:05 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127398 is cancelled at 1120 hrs 05/06/2025.

Manager NEM Real Time Operations
     
127398RESERVE NOTICE05/06/2025 05:16:54 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 127390 has been updated at 0520 hrs to the following:

[1.] From 1800 hrs 05/06/2025 to 1930 hrs 05/06/2025.
The forecast capacity reserve requirement is 730 MW.
The minimum capacity reserve available is 681 MW.


Manager NEM Real Time Operations
     
127397RESERVE NOTICE04/06/2025 07:40:01 PM

Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 04/06/2025

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.127394 is cancelled at 1945 hrs 04/06/2025.

Manager NEM Real Time Operations
     
127395RESERVE NOTICE04/06/2025 06:47:22 PM

Cancellation of Actual (LOR1) condition in the NSW region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 04/06/2025

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.127393 is cancelled at 1845 hrs 04/06/2025.

Manager NEM Real Time Operations
     
127394RESERVE NOTICE04/06/2025 06:14:34 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 730 MW
The minimum capacity reserve available is 682 MW

Manager NEM Real Time Operations
     
127393RESERVE NOTICE04/06/2025 05:41:44 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/06/2025

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 04/06/2025

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs

The capacity reserve requirement is 1540 MW
The minimum capacity reserve available is 1540 MW

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm