Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 01/06/2025
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 01/06/2025
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The forecast capacity reserve requirement is 1694 MW.
The minimum capacity reserve available is 1568 MW.
Manager NEM Real Time Operations
Resolved - INC0145274 - Markets Portal - Unable to View Menu
SERVICE INTERRUPTION - RESOLVED
The service interruption relating to the Market Portal has been resolved.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
Completed - CHG0103591 - Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Cancellation - AEMO Intervention Event - SA region 22/05/2025
Cancellation - AEMO Intervention Event - SA region 22/05/2025
Refer to Market Notice 127159
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 27/05/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127276
Direction is cancelled from: 1400 hrs 27/05/2025
Manager NEM Real Time Operations
Initial - CHG0103591 - Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: Pre-Prod MSATS 54.2 CICD Maintenance Release (MSATS App deployment only)
Change Start Date & Time: 28/05/2025 13:00:00
Change End Date & Time: 28/05/2025 17:00:00
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: no outage, deployment will be made to msats 1a first then switch to msats 1b.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127232
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1400 hrs 27/05/2025.
The direction update is issued at 1600 hrs 26/05/2025.
Manager NEM Real Time Operations
Completed - CHG0103179 - Scheduled maintenance of Marketnet router in Brisbane
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Local Area Network
Change Title: Scheduled maintenance of Marketnet router in Brisbane
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 127193
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 27/05/2025.
The direction update is issued at 1600 hrs 25/05/2025.
Manager NEM Real Time Operations