Cancellation - Inter-regional transfer limit variation: Hazelwood - South Morang No.2 500 kV Line (Vic) - Voltage Control
Cancellation - Inter-regional transfer limit variation: Hazelwood - South Morang No.2 500 kV Line (Vic) - Voltage Control
Refer AEMO Electricity Market Notice 75090
The Hazelwood - South Morang No.2 500 kV Line has been returned to service.
The following constraint set was revoked at 0510 hrs 01/04/2020.
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1
Manager NEM Real Time Operations
Inter-regional transfer limit variation: Hazelwood - South Morang No 2 500 kV Line (VIC) - Voltage Control
The Hazelwood - South Morang No 2 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 0205 hrs 01/04/2020
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further details
Manager NEM Real Time Operations
CHG0058714 : Telco Outage Notification - Telstra MarketNet IP WAN - NSW (Telstra ref: 2990535)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market VPN
Change Title: Telco Outage Notification - Telstra MarketNet IP WAN - NSW (Telstra ref: 2990535)
Change Start Date & Time: 06/04/2020 02:00:00 AEST
Change End Date & Time: 06/04/2020 07:00:00 AEST
Outage Start Date & Time: 06/04/2020 02:00:00 AEST
Outage End Date & Time: 06/04/2020 07:00:00 AEST
Change Description:
Planned Maintenance Affecting the AEMO MarketNet IPWAN Access.
Environment: Production
Participant Impact and Requirements:
The following impacts are expected to participant connectivity during this planned outage:-
o IPWAN Participants - loss of redundancy for 10 minutes
o VPN Participants - nil
o Remote Access VPN Participants - nil
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
RESERVE NOTICE MT PASA PUBLICATION 31 March 2020
Please note that MTPASA informs the market of potential reliability issues to allow the market to respond in the first instance, potentially avoiding the need for any market intervention or direction from AEMO.
For further information, please refer to:
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Data/Market-Management-System-MMS/Projected-Assessment-of-System-Adequacy
This notice supersedes Market Notice 75014 published published on 25 March 2020.
Background
As part of a broader process of implementing the reliability standard, AEMO runs the Medium Term Projected Assessment of System Adequacy (MTPASA) process weekly to forecast expected unserved energy levels over a two year period. If the expected annual unserved energy exceeds the maximum level specified by the Reliability Standard, a Low Reserve Condition is identified.
For more information about how AEMO implements the reliability standard, please view the Reliability Standard Implementation Guidelines (RSIG) available on AEMO's website at
https://www.aemo.com.au/Electricity/National-Electricity-Market-NEM/Planning-and-forecasting/Reliability-Standard-Implementation-Guidelines
Forecasting
AEMO
Cancellation - Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500 kV Line (Vic) - Voltage Control
Cancellation - Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500 kV Line (Vic) - Voltage Control
Refer AEMO Electricity Market Notice 75085
The Hazelwood - South Morang No.1 500 kV Line has been returned to service.
The following constraint set was revoked at 0530 hrs 31/03/2020.
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV
Cancellation time: 30/03/2020 23:59
Constraint set(s) revoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1
Refer AEMO Electricity Market Notice 75084
Auto-generated on behalf of Manager NEM Real Time Operations
Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control
The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.
The following constraint set was invoked at 2230 hrs 30/03/2020
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Scheduler (NOS) for further details
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV
Duration: 30/03/2020 21:55 until further notice
Constraint set(s) invoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV
Cancellation time: 30/03/2020 19:19
Constraint set(s) revoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1
Refer AEMO Electricity Market Notice 75082
Auto-generated on behalf of Manager NEM Real Time Operations