Market Notices

75112RECLASSIFY CONTINGENCY03/04/2020 07:55:45 PM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 03/04/2020 19:55 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
75111RECLASSIFY CONTINGENCY03/04/2020 07:55:45 PM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Duration: 03/04/2020 19:55 until further notice

Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
75110RECLASSIFY CONTINGENCY03/04/2020 07:55:45 PM

Reclassification of a Non-Credible Contingency Event: Farrell-Sheffield No.1 220 kV line and Farrell-Sheffield No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-Sheffield No.1 220 kV and Farrell-Sheffield No.2 220 kV

Duration: 03/04/2020 19:55 until further notice

Constraint set(s) invoked:
F-T-FASH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-FASH_N-2_CP4_S3 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
75109GENERAL NOTICE03/04/2020 05:18:03 PM

Non-credible contingency event more likely to occur due to existence of abnormal conditions - SA region

AEMO ELECTRICITY MARKET NOTICE.

AEMO has identified that a non-credible contingency event is more likely to occur because of the existence of abnormal conditions, namely damaging winds in the South Australia region

As at the time of this notice the criteria for reclassification of any non-credible contingency event have not been met, however there is a possibility of severe weather impacting multiple transmission elements in its vicinity.

Conditions can change rapidly and potentially impacted plant may change. Further notices will only be published to advise of any reclassification, or when the abnormal conditions have ceased to impact the likelihood of a non-credible event occurring.

Constraint set I-VS_250 invoked at 1715 hrs 3/04/2020 until further notice.


Manager NEM Real Time Operations
75106MARKET INTERVENTION03/04/2020 05:04:10 PM

Direction - SA region - 3/04/2020

AEMO ELECTRICITY MARKET NOTICE.

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all dispatch intervals during the event to be intervention dispatch intervals, commencing from the interval ending 1705 hrs on 3/04/2020.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
75104MARKET INTERVENTION03/04/2020 03:20:40 PM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

The synchronous generating units expected to be synchronised in SA from 0200 hrs 4/04/2020 to 1530 hrs 4/04/2020 in Pre-dispatch published at 1500 hrs 3/04/2020 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response by 1700 hrs 3/04/2020, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
75103RECLASSIFY CONTINGENCY03/04/2020 12:11:24 PM

Reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly, AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Duration: 1205 hrs 03/04/2020 until further notice

Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
75102RECLASSIFY CONTINGENCY03/04/2020 12:11:04 PM

Reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Duration: 1205 hrs 03/04/2020 until further notice

Constraint set(s) invoked: Nil

Manager NEM Real Time Operations
75101INTER-REGIONAL TRANSFER03/04/2020 05:40:53 AM

Cancellation - Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500 kV Line (Vic) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500 kV Line (Vic) - Voltage Control

Refer AEMO Electricity Market Notice 75100

The Hazelwood - South Morang No.1 500 kV Line has been returned to service.

The following constraint set was revoked at 0540 hrs 03/04/2020.

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1

Manager NEM Real Time Operations