Market Notices

74886MARKET SYSTEMS12/03/2020 01:50:20 PM

AEMO Help Desk Bulletin No. 2441 : CHG0058392 : Telco Outage Notification - Telstra MarketNet IP WAN - NSW (Telstra ref: 2968873)

Change Number: CHG0058392

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Market Network

Change Title: Telco Outage Notification - Telstra MarketNet IP WAN - NSW (Telstra ref: 2968873)

Change Start Date & Time: 17/03/2020 09:00:00 AEST

Change End Date & Time: 18/03/2020 05:00:00 AEST

Outage Start Date & Time: 17/03/2020 23:00:00 AEST

Outage End Date & Time: 18/03/2020 05:00:00 AEST

Change Description:

Planned Maintenance Affecting the AEMO MarketNet IPWAN Access.

Environment: Production

Participant Impact and Requirements:

The following impacts are expected to participant connectivity during this planned outage:-
o IPWAN Participants - loss of redundancy for 2.5 hours
o VPN Participants - nil
o Remote Access VPN Participants - nil

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
74885MARKET INTERVENTION12/03/2020 05:18:59 PM

Direction - SA Region - 12/03/2020

AEMO ELECTRICITY MARKET NOTICE.

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event.

AEMO declares all dispatch intervals during the event to be intervention dispatch intervals, commencing from the interval ending 0005 hrs on 13/03/2020.

Intervention pricing does not apply to this AEMO intervention event.


Manager NEM Real Time Operations
74882MARKET INTERVENTION12/03/2020 09:31:32 AM

Possible intervention to manage power system security in South Australia (SA) Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in South Australia (SA) Region

The synchronous generating units expected to be synchronised in SA from 0030 hrs 13 Mar 2020 to 1400 hrs 13 Mar 2020 in Pre-dispatch published at 0900hrs 12 Mar 2020 are inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO currently estimates that, in the absence of sufficient market response by 1700 hrs 12 Mar 2020, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
74881RECLASSIFY CONTINGENCY11/03/2020 11:44:12 PM

Cancellation of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Cancellation time: 11/03/2020 23:44

Constraint set(s) revoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 74880

Auto-generated on behalf of Manager NEM Real Time Operations
74880RECLASSIFY CONTINGENCY11/03/2020 10:43:50 PM

Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Duration: 11/03/2020 22:43 until further notice

Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
74879RECLASSIFY CONTINGENCY11/03/2020 08:59:10 PM

Cancellation of a Non-Credible Contingency Event: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV line and Goonyella - Newlands No. 7155 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV and Goonyella - Newlands No. 7155 132 kV

Cancellation time: 11/03/2020 20:59

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 74878

Auto-generated on behalf of Manager NEM Real Time Operations
74878RECLASSIFY CONTINGENCY11/03/2020 07:57:16 PM

Reclassification of a Non-Credible Contingency Event: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV line and Goonyella - Newlands No. 7155 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Goonyella - Nth Goonyella T- Stoney Creek 7122 132 kV and Goonyella - Newlands No. 7155 132 kV

Duration: 11/03/2020 19:57 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
74877MARKET SYSTEMS11/03/2020 05:19:09 PM

CHG0058400: Pre-Prod SMP database servers maintenance activity

Change Number: CHG0058400

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: MSATS - Business to Business data exchange

Change Title: Pre-Prod SMP database servers maintenance activity

Change Start Date & Time: 12/03/2020 10:00:00 AEST

Change End Date & Time: 12/03/2020 11:00:00 AEST

Outage Start Date & Time: 12/03/2020 10:00:00 AEST

Outage End Date & Time: 12/03/2020 11:00:00 AEST

Change Description:

Outage of pre-production Electricity and Gas Hub systems for maintenance activities.

Environment: Pre-Production

Participant Impact and Requirements:

Electricity and Gas Hub systems will be unavailble briefly during the change window.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
74876NON-CONFORMANCE11/03/2020 07:05:16 AM

NON-CONFORMANCE Region NSW1 Wednesday, 11 March 2020

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Wednesday, 11 March 2020

AEMO declared a schedule generating unit non-conforming

Unit: VP6
Duration: 11/03/2020 06:45 to 11/03/2020 07:05
Amount: -14 MW
Constraint: NC-N_VP6

Auto-generated on behalf of Manager NEM Real Time Operations