88410MARKET INTERVENTION19/07/2021 01:26:47 PM

Update - Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA Region

Refer to MN 88341

The synchronous generating units currently expected to be synchronised in SA from 2200 hrs 19/07/2021 to 1630 hrs 20/07/2021 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 19/07/2021, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
88409RESERVE NOTICE19/07/2021 11:44:12 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/07/2021

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1800 hrs 19/07/2021 to 1900 hrs 19/07/2021
The forecast capacity reserve requirement is 1102 MW.
The minimum capacity reserve available is 1052 MW.

Manager NEM Real Time Operations
88408RESERVE NOTICE19/07/2021 10:17:57 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/07/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No 88402 is cancelled at 1010 hrs 19/07/2021.

Manager NEM Real Time Operations
88407RESERVE NOTICE19/07/2021 10:41:31 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 20/07/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 conditions in the NSW region advised in AEMO Electricity Market Notice No. 88348 have been updated at 1000 hrs 19/07/2021 to the following:

[1.] From 1800 hrs 21/07/2021 to 1900 hrs 21/07/2021.
The forecast capacity reserve requirement is 1498 MW.
The minimum capacity reserve available is 1192 MW.

[2.] From 0730 hrs 22/07/2021 to 0800 hrs 22/07/2021.
The forecast capacity reserve requirement is 1240 MW.
The minimum capacity reserve available is 1128 MW.

The Forecast LOR2 condition on 20/07/2021 in the NSW region advised in AEMO Electricity Market Notice No. 88348 is cancelled.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
88406RESERVE NOTICE19/07/2021 10:40:21 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region beginning on 20/07/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 88338 and 88347 are cancelled at 1000 hrs 19/07/2021.

AEMO Operations
88405RESERVE NOTICE19/07/2021 09:57:37 AM

Correction - PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 19/07/2021

AEMO ELECTRICITY MARKET NOTICE

This is a correction to MN 88393.

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 88362 is cancelled at 0820 hrs 19/07/2021.

Manager NEM Real Time Operations
88404RESERVE NOTICE19/07/2021 09:39:24 AM

Cancellation of Actual (LOR1) condition in the NSW region - 19/07/2021

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 19/07/2021

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.88386 is cancelled at 0940hrs 19/07/2021

Manager NEM Real Time Operations
88403NEM SYSTEMS19/07/2021 09:07:46 AM

INC0072513 : Marketnet VPN at Norwest having intermittent issues - Resolved

AEMO ELECTRICITY MARKET NOTICE
INC0072513 - Marketnet VPN at Norwest having intermittent issues - Resolved

Participants should now be able to connect to the Norwest site-site VPN
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
88402RESERVE NOTICE19/07/2021 08:55:40 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/07/2021

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 88395 has been updated at 0850 hrs to the following:

From 1800 hrs 19/07/2021 to 1830 hrs 19/07/2021
The forecast capacity reserve requirement is 1088 MW.
The minimum capacity reserve available is 1076 MW.