STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/07/2021
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1800 hrs 26/07/2021 to 1900 hrs 26/07/2021.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 591 MW.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 20/07/2021
The Forecast LOR1 conditions in the QLD region advised in AEMO Electricity Market Notice No. 88337 are cancelled at 1500 hrs 19/07/2021.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 21/07/2021
The Forecast LOR2 conditions in the NSW region advised in AEMO Electricity Market Notice No. 88407 have been updated at 1500 hrs 19/07/2021 to the following:
From 0730 hrs 22/07/2021 to 0800 hrs 22/07/2021.
The forecast capacity reserve requirement is 1392 MW.
The minimum capacity reserve available is 1294 MW.
The Forecast LOR2 condition on 21/07/2021 in the NSW region advised in AEMO Electricity Market Notice No. 88407 is cancelled at 1400 hrs on 19/07/2021.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Update: Cancellation of planned outage of Heywood 500kV no 1 busbar and Heywood - Tarrone 500kV line outage in Victoria region(VIC) on 31 July 2021
Refer to AEMO Electricity Market notice 88287
The Heywood No.1 500 kV busbar and Heywood-Tarrone 500kV line in Victoria (VIC) Region was planned out of serviice on 31/07/2021. This outage is now cancelled.
All constraint sets associated with this outage have been revoked.
AEMO operations
NON-CONFORMANCE Region NSW1 Monday, 19 July 2021
NON-CONFORMANCE NSW1 Region Monday, 19 July 2021
AEMO declared a schedule generating unit non-conforming
Unit: VP5
Duration: 19/07/2021 13:50 to 19/07/2021 14:00
Amount: 39 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/07/2021
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No 88388 is cancelled at 1345 hrs 19/07/2021.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/07/2021
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No 88409 is cancelled at 1345 hrs 19/07/2021.
Manager NEM Real Time Operations
Update - Possible intervention to manage power system security in SA Region
Update - Possible intervention to manage power system security in SA Region
Refer to MN 88341
The synchronous generating units currently expected to be synchronised in SA from 2200 hrs 19/07/2021 to 1630 hrs 20/07/2021 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO estimates that, in the absence of sufficient market response by 1630 hrs 19/07/2021, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 19/07/2021
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1800 hrs 19/07/2021 to 1900 hrs 19/07/2021
The forecast capacity reserve requirement is 1102 MW.
The minimum capacity reserve available is 1052 MW.
Manager NEM Real Time Operations