[EventId:202505131405_confirmed] Prices for interval 13-May-2025 14:05 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1415 hrs on 13 May 2025
PRICES ARE NOW CONFIRMED for trading interval 13-May-2025 14:05.
In accordance with Market Notice 127015 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202505131400_confirmed] Prices for interval 13-May-2025 14:00 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1415 hrs on 13 May 2025
PRICES ARE NOW CONFIRMED for trading interval 13-May-2025 14:00.
In accordance with Market Notice 127014 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202505131355_confirmed] Prices for interval 13-May-2025 13:55 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1415 hrs on 13 May 2025
PRICES ARE NOW CONFIRMED for trading interval 13-May-2025 13:55.
In accordance with Market Notice 127013 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127006 is cancelled at 2035 hrs 12/05/2025
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127003 has been updated at 1600 hrs 12/05/2025 to the following:
1. From 1130 hrs to 1200 hrs 15/05/2025.
The forecast capacity reserve requirement is 459 MW.
The minimum capacity reserve available is 457 MW.
2. From 1430 hrs to 1530 hrs 15/05/2025.
The forecast capacity reserve requirement is 467 MW.
The minimum capacity reserve available is 456 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 126998 has been updated at 1500 hrs 12/05/2025 to the following:
From 1430 hrs to 1500 hrs 15/05/2025.
The forecast capacity reserve requirement is 461 MW.
The minimum capacity reserve available is 453 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 15/05/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1030 hrs to 1230 hrs 15/05/2025.
The forecast capacity reserve requirement is 438 MW.
The minimum capacity reserve available is 401 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Cancellation of a Non-Credible Contingency Event: Kamerunga - Barron Gorge 7184 132kV line and Kamerunga - Barron Gorge 7143 132kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Kamerunga - Barron Gorge 7184 132kV and Kamerunga - Barron Gorge 7143 132kV
Cancellation time: 12/05/2025 04:39
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 126993
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Kamerunga - Barron Gorge 7184 132kV line and Kamerunga - Barron Gorge 7143 132kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Kamerunga - Barron Gorge 7184 132kV and Kamerunga - Barron Gorge 7143 132kV
Duration: 12/05/2025 03:35 until further notice
Constraint set(s) invoked:
NONE