Market Notices

117053INTER-REGIONAL TRANSFER18/06/2024 03:19:21 PM

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Collector Wind Farm to Yass 3L 330kV line - NSW region - 18/06/2024

A planned outage of Collector Wind Farm to Yass 3L 330kV line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1500 hrs 08/07/2024.

The outage has been completed and Collector Wind Farm to Yass 3L 330kV line returned to service at 1515 hrs 18/06/2024

Constraint set revoked: N-CTYS_3L_WG_CLOSE

Manager NEM Real Time Operations
     
117048RESERVE NOTICE18/06/2024 02:47:53 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.117033 has been updated at 1500 hrs to the following:

[1.] From 1800 hrs 18/06/2024 to 1900 hrs 18/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1628 MW.


Manager NEM Real Time Operations
     
117046RESERVE NOTICE18/06/2024 01:00:03 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:

[1.] From 1700 hrs 19/06/2024 to 1730 hrs 19/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1385 MW.

[2.] From 1930 hrs 19/06/2024 to 2100 hrs 19/06/2024.
The forecast capacity reserve requirement is 1750 MW.
The minimum capacity reserve available is 1146 MW.

Manager NEM Real Time Operations
     
117045RESERVE NOTICE18/06/2024 01:01:16 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 19/06/2024 to 1930 hrs 19/06/2024.
The forecast capacity reserve requirement is 1052 MW.
The minimum capacity reserve available is 851 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
117041RESERVE NOTICE18/06/2024 10:15:06 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 21/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 0000 hrs to 0100 hrs 21/06/2024.
The forecast capacity reserve requirement is 1321 MW.
The minimum capacity reserve available is 1050 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
117040RESERVE NOTICE18/06/2024 10:13:46 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region for 20/06/2024 advised in AEMO Electricity Market Notice No. 117036 has been updated at 0900 hrs 18/06/2024 to the following:

1. From 0530 hrs to 0930 hrs 20/06/2024.
The forecast capacity reserve requirement is 1318 MW.
The minimum capacity reserve available is 798 MW.

2. From 1530 hrs to 2359 hrs 20/06/2024.
The forecast capacity reserve requirement is 1248 MW.
The minimum capacity reserve available is 733 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
117039RESERVE NOTICE18/06/2024 10:12:10 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 117038 has been updated at 0900 hrs 18/06/2024 to the following:

From 1700 hrs to 2030 hrs 19/06/2024.
The forecast capacity reserve requirement is 1190 MW.
The minimum capacity reserve available is 789 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
117038RESERVE NOTICE18/06/2024 08:46:21 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 117035 has been updated at 0840 hrs 18/06/2024 to the following:

[1.] From 1730 hrs 19/06/2024 to 2000 hrs 19/06/2024.
The forecast capacity reserve requirement is 1114 MW.
The minimum capacity reserve available is 812 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.



Manager NEM RTO
     
117036RESERVE NOTICE18/06/2024 05:40:52 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 20/06/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region for 20/06/2024 advised in AEMO Electricity Market Notice No. 117034 has been updated at 0540 hrs 18/06/2024 to the following:

[1.] From 0600 hrs 20/06/2024 to 0930 hrs 20/06/2024.
The forecast capacity reserve requirement is 1203 MW.
The minimum capacity reserve available is 848 MW.

[2.] From 1530 hrs 20/06/2024 to 0100 hrs 21/06/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 781 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     