Market Notices

116915MARKET INTERVENTION09/06/2024 02:19:23 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116914

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 10/06/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 09/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116914MARKET INTERVENTION09/06/2024 12:37:49 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 10/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116899GENERAL NOTICE05/06/2024 12:11:55 PM

Network Augmentation Commissioned - QLD Region - 05/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 05/06/2024

H20 Broadsound 275 kV Bus Reactor 1 (150 MVAr) has been commissioned as at 1043 hrs.

Manager NEM Real Time Operations
     
116890PRICES SUBJECT TO REVIEW04/06/2024 06:55:22 PM

[EventId:202406041900_review] Prices for interval 04-Jun-2024 19:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1855 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 19:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116889PRICES SUBJECT TO REVIEW04/06/2024 06:50:22 PM

[EventId:202406041855_review] Prices for interval 04-Jun-2024 18:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1850 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116888PRICES SUBJECT TO REVIEW04/06/2024 06:45:24 PM

[EventId:202406041850_review] Prices for interval 04-Jun-2024 18:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1845 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116887PRICES SUBJECT TO REVIEW04/06/2024 06:40:24 PM

[EventId:202406041845_review] Prices for interval 04-Jun-2024 18:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1840 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116886PRICES SUBJECT TO REVIEW04/06/2024 06:35:16 PM

[EventId:202406041840_review] Prices for interval 04-Jun-2024 18:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116885PRICES SUBJECT TO REVIEW04/06/2024 06:30:17 PM

[EventId:202406041835_review] Prices for interval 04-Jun-2024 18:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm