Market Notices

116898INTER-REGIONAL TRANSFER04/06/2024 09:36:26 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 2135 hrs 04/06/2024

N-MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
116897INTER-REGIONAL TRANSFER04/06/2024 07:45:46 PM

Inter-Regional Transfer limit variation - Directlink - NSW Region

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink - NSW Region

There has been an unplanned outage of the No 1 Leg of Directlink .

The following constraint set was invoked at 1945 hrs 04/06/2024

N-MBTE_2

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1

Refer AEMO Network Outage Scheduler (NOS) for further details.

Manager NEM Real Time Operations
     
116890PRICES SUBJECT TO REVIEW04/06/2024 06:55:22 PM

[EventId:202406041900_review] Prices for interval 04-Jun-2024 19:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1855 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 19:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116889PRICES SUBJECT TO REVIEW04/06/2024 06:50:22 PM

[EventId:202406041855_review] Prices for interval 04-Jun-2024 18:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1850 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116888PRICES SUBJECT TO REVIEW04/06/2024 06:45:24 PM

[EventId:202406041850_review] Prices for interval 04-Jun-2024 18:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1845 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116887PRICES SUBJECT TO REVIEW04/06/2024 06:40:24 PM

[EventId:202406041845_review] Prices for interval 04-Jun-2024 18:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1840 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116886PRICES SUBJECT TO REVIEW04/06/2024 06:35:16 PM

[EventId:202406041840_review] Prices for interval 04-Jun-2024 18:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116885PRICES SUBJECT TO REVIEW04/06/2024 06:30:17 PM

[EventId:202406041835_review] Prices for interval 04-Jun-2024 18:35 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 4 June 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 04-Jun-2024 18:35.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116878RECLASSIFY CONTINGENCY02/06/2024 04:54:31 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 02/06/2024 16:54

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 116876

Auto-generated on behalf of Manager NEM Real Time Operations
     