Filter by category
Filter by Date
[EventId:202505061920_review] Prices for interval 06-May-2025 19:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1915 hrs on 6 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-May-2025 19:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505061915_review] Prices for interval 06-May-2025 19:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1910 hrs on 6 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-May-2025 19:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505061910_review] Prices for interval 06-May-2025 19:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1905 hrs on 6 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-May-2025 19:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505061905_review] Prices for interval 06-May-2025 19:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 6 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-May-2025 19:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505061900_review] Prices for interval 06-May-2025 19:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1855 hrs on 6 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-May-2025 19:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505061855_review] Prices for interval 06-May-2025 18:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1850 hrs on 6 May 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 06-May-2025 18:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202505061700_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 06 May 2025 17:00
Issued by Australian Energy Market Operator Ltd at 1700 hrs on 6 May 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 6 May 2025.
Refer to market notice: 126908
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1700 hrs on 6 May 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202505061620_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 06 May 2025 16:20
Issued by Australian Energy Market Operator Ltd at 1620 hrs on 6 May 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 6 May 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1620 hrs on 6 May 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer to Market Notice 126848
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 06/05/2025
Type of resource: generating unit
Required actions: To synchronise and follow dispatch targets at 1200 hrs 07/05/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/05/2025.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations