117034RESERVE NOTICE17/06/2024 10:40:41 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region beginning on 19/06/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 0530 hrs 19/06/2024 to 0900 hrs 19/06/2024.
The forecast capacity reserve requirement is 1050 MW.
The minimum capacity reserve available is 712 MW.

[2.] From 1600 hrs 19/06/2024 to 0130 hrs 20/06/2024.
The forecast capacity reserve requirement is 1082 MW.
The minimum capacity reserve available is 592 MW.

[3.] From 0530 hrs 20/06/2024 to 1000 hrs 20/06/2024.
The forecast capacity reserve requirement is 1250 MW.
The minimum capacity reserve available is 674 MW.

[4.] From 1600 hrs 20/06/2024 to 0100 hrs 21/06/2024.
The forecast capacity reserve requirement is 1253 MW.
The minimum capacity reserve available is 591 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
117021RESERVE NOTICE15/06/2024 08:03:58 PM

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 15/06/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.117020 is cancelled at 1900 hrs 15/06/2024.

Manager NEM Real Time Operations
     
117020RESERVE NOTICE15/06/2024 05:14:10 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 15/06/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1780 MW
The minimum capacity reserve available is 1446 MW

Manager NEM Real Time Operations
     
117014MARKET INTERVENTION14/06/2024 08:29:53 PM

Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in QLD region 14/06/2024

Refer Market Notice 116996

AEMO no longer foresees a possible requirement for intervention to manage power system security in QLD region. The advice of possible intervention is cancelled from 2030 hrs 14/06/2024.

Manager NEM Real Time Operations
     
116996MARKET INTERVENTION14/06/2024 03:21:35 PM

Possible intervention to manage power system security in QLD Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in QLD region

The synchronous generating units currently expected to be synchronised in North QLD from 2100 hrs 14/06/2024 will be inadequate to maintain a secure operating state in North QLD.

AEMO estimates that, in the absence of sufficient market response by 2030 hrs 14/06/2024, AEMO may need to intervene by issuing a direction requiring one or more North QLD synchronous generating unit(s) to operate or remain synchronised to maintain power system security in QLD.

Manager NEM Real Time Operations
     
116989MARKET INTERVENTION13/06/2024 10:00:13 PM

Cancellation - AEMO Intervention Event: Intervention trading intervals - Direction QLD region 13/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event: Intervention trading intervals - Direction QLD region 13/06/2024

Refer Market Notice 116987

The AEMO Intervention Event and all associated directions are cancelled from 2200 hrs 13/06/2024

Manager NEM Real Time Operations
     
116987MARKET INTERVENTION13/06/2024 08:30:12 PM

Direction - QLD region 13/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - QLD region 13/06/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the QLD region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 2035 hrs on 13/06/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
     
116985MARKET INTERVENTION13/06/2024 05:29:34 PM

Possible intervention to manage power system security in QLD Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in QLD region

The synchronous generating units currently expected to be synchronised in North QLD from 2100 hrs 13/06/2024 will be inadequate to maintain a secure operating state in North QLD.

AEMO estimates that, in the absence of sufficient market response by 2030 hrs 13/06/2024, AEMO may need to intervene by issuing a direction requiring one or more North QLD synchronous generating unit(s) to operate or remain synchronised to maintain power system security in QLD.

Manager NEM Real Time Operations



     
116967MARKET INTERVENTION12/06/2024 04:18:47 AM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 11/06/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 11/06/2024

Refer Market Notice 116945

The AEMO Intervention Event and all associated directions are cancelled from 0430 hrs 12/06/2024

Manager NEM Real Time Operations
     