Market Notices

116918MARKET INTERVENTION09/06/2024 04:00:37 PM

Direction - SA region 09/06/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 09/06/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 09/06/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
     
116915MARKET INTERVENTION09/06/2024 02:19:23 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116914

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 10/06/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 09/06/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116914MARKET INTERVENTION09/06/2024 12:37:49 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 10/06/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116899GENERAL NOTICE05/06/2024 12:11:55 PM

Network Augmentation Commissioned - QLD Region - 05/06/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 05/06/2024

H20 Broadsound 275 kV Bus Reactor 1 (150 MVAr) has been commissioned as at 1043 hrs.

Manager NEM Real Time Operations
     
116896PRICES UNCHANGED04/06/2024 07:03:32 PM

[EventId:202406041900_confirmed] Prices for interval 04-Jun-2024 19:00 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 4 June 2024

PRICES ARE NOW CONFIRMED for trading interval 04-Jun-2024 19:00.

In accordance with Market Notice 116890 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116895PRICES UNCHANGED04/06/2024 07:02:22 PM

[EventId:202406041855_confirmed] Prices for interval 04-Jun-2024 18:55 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 4 June 2024

PRICES ARE NOW CONFIRMED for trading interval 04-Jun-2024 18:55.

In accordance with Market Notice 116889 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116894PRICES UNCHANGED04/06/2024 07:05:41 PM

[EventId:202406041850_confirmed] Prices for interval 04-Jun-2024 18:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 4 June 2024

PRICES ARE NOW CONFIRMED for trading interval 04-Jun-2024 18:50.

In accordance with Market Notice 116888 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116893PRICES UNCHANGED04/06/2024 07:01:24 PM

[EventId:202406041845_confirmed] Prices for interval 04-Jun-2024 18:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 4 June 2024

PRICES ARE NOW CONFIRMED for trading interval 04-Jun-2024 18:45.

In accordance with Market Notice 116887 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
116892PRICES UNCHANGED04/06/2024 07:00:22 PM

[EventId:202406041840_confirmed] Prices for interval 04-Jun-2024 18:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 4 June 2024

PRICES ARE NOW CONFIRMED for trading interval 04-Jun-2024 18:40.

In accordance with Market Notice 116886 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm