Load Restoration Direction Cancellation in the Vic Region
Cancellation - Load Restoration Direction in the Vic Region - 13/02/2024
Refer to AEMO Electricity Market Notice ID 114607
Load restoration as directed is complete. Direction cancelled from 1510 hrs 13/02/2024.
Manager NEM Real Time Operations
Load Restoration Direction in the Vic Region
Load Restoration Direction in the Vic Region
AEMO has directed load restoration commencing at 1450 hrs 13/02/2024 in the Victoria region
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations
Load Shedding Direction in the Vic Region
Load Shedding Direction in the Vic Region
AEMO has directed load shedding commencing at 1420 hrs 13/02/2024
in the Victoria region to restore power system security.
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations
Cancellation: Protected event advice - South Australia region.
AEMO has identified that the conditions of the following protected event are no longer met.
Protected event: the loss of multiple transmission elements causing generation disconnection in the South Australia region during periods where destructive wind conditions are forecast by the Bureau of Meteorology.
Cancellation: 07/06/2023 2100hrs
Constraint set revoked: I-VS_250
Refer AEMO Electricity Market Notice 108385
Manager NEM Real Time Operations
Protected event advice - South Australia region.
AEMO has identified that the conditions of the following protected event will be met from the time specified in this notice.
Protected event: the loss of multiple transmission elements causing generation disconnection in the South Australia region during periods where destructive wind conditions are forecast by the Bureau of Meteorology.
Duration: 07/06/2023 1230 hrs until further notice
AEMO will take action to manage the power system for the impact of the protected event.
Constraint set invoked: I-VS_250
Manager NEM Real Time Operations
Cancellation: Protected event advice - South Australia region.
AEMO has identified that the conditions of the following protected event are no longer met.
Protected event: the loss of multiple transmission elements causing generation disconnection in the South Australia region during periods where destructive wind conditions are forecast by the Bureau of Meteorology.
Cancellation: 2100 hrs 30/10/2022
Constraint set revoked: I-VS_250
Refer AEMO Electricity Market Notice 102723
Manager NEM Real Time Operations
Cancellation: Protected event advice - South Australia region.
AEMO has identified that the conditions of the following protected event are no longer met.
Protected event: the loss of multiple transmission elements causing generation disconnection in the South Australia region during periods where destructive wind conditions are forecast by the Bureau of Meteorology.
Cancellation: 0530 hrs 05/06/2022
Constraint set revoked: I-VS_250
Refer AEMO Electricity Market Notice 96776
Manager NEM Real Time Operations
Protected event advice - South Australia region.
AEMO has identified that the conditions of the following protected event will be met from the time specified in this notice.
Protected event: the loss of multiple transmission elements causing generation disconnection in the South Australia region during periods where destructive wind conditions are forecast by the Bureau of Meteorology.
Duration: 1915 hrs 04/06/2022 until further notice
AEMO will take action to manage the power system for the impact of the protected event.
Constraint set(s) invoked: I-VS_250
Manager NEM Real Time Operations
Cancellation: Protected event advice - South Australia region.
AEMO has identified that the conditions of the following protected event are no longer met.
Protected event: the loss of multiple transmission elements causing generation disconnection in the South Australia region during periods where destructive wind conditions are forecast by the Bureau of Meteorology.
Cancellation: 26/01/2022 2300 hrs
Constraint set(s) revoked: I-VS_250
Refer AEMO Electricity Market Notice 94056
Manager NEM Real Time Operations