Market Notices

126830MARKET INTERVENTION01/05/2025 08:20:53 AM

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126810

PPCCGT PELICAN POINT at 0930 hrs 01/05/2025 to Remain synchronised and follow dispatch targets.

The PPCCGT PELICAN POINT direction is expected to stay in place until 1500 hrs 01/05/2025.

The direction update is issued at 0820 hrs 01/05/2025.

Manager NEM Real Time Operations
     
126814MARKET INTERVENTION30/04/2025 05:25:48 PM

Cancellation - AEMO Intervention Event - SA region 29/04/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 29/04/2025

Refer to Market Notice 126779

The AEMO Intervention Event and all associated directions are cancelled from 1725 hrs on 30/04/2025.


Manager NEM Real Time Operations
     
126813MARKET INTERVENTION30/04/2025 05:25:38 PM

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126782

Direction is cancelled from: 1725 hrs 30/04/2025

Manager NEM Real Time Operations
     
126812INTER-REGIONAL TRANSFER30/04/2025 04:31:48 PM

Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Red Cliffs - Buronga X1 220kV Line - NSW region - 30/04/2025

A planned outage of Red Cliffs - Buronga X1 220kV Line in the NSW region was scheduled from 0700 hrs 27/04/2025 to 1700 hrs 02/05/2025.

The outage has been completed and Red Cliffs - Buronga X1 220kV Line returned to service at 1625 hrs 30/04/2025

Constraint set(s) revoked: I-BURC_X1

Manager NEM Real Time Operations
     
126810MARKET INTERVENTION30/04/2025 04:02:12 PM

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to Pelican Point Power Limited - PPCCGT PELICAN POINT

Refer to Market Notice 126809.


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to Pelican Point Power Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: Pelican Point Power Limited - PPCCGT PELICAN POINT at 1600 hrs 30/04/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 0830 hrs 01/05/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 1500 hrs 01/05/2025.

Pelican Point Power Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
126809MARKET INTERVENTION30/04/2025 04:01:28 PM

Direction - SA region 30/04/2025

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 30/04/2025

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 30/04/2025.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.



Manager NEM Real Time Operations
     
126808MARKET INTERVENTION30/04/2025 03:15:08 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 126802

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 01/05/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 30/04/2025, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
126802MARKET INTERVENTION30/04/2025 01:00:15 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0830 hrs 01/05/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
126786CONSTRAINTS29/04/2025 05:43:58 PM

Updated Victorian system normal voltage stability limit for the south-west Victoria

AEMO ELECTRICITY MARKET NOTICE

Refer to Market Notice 101368

AEMO has completed a review of the system normal voltage stability limit in the south-west Victoria as a result of Mortlake terminal station cut-in on the Haunted Gully to Tarrone 500 kV line.

The revised limit is increased by 100 MW on the cut-set from Haunted Gully to Moorabool and Mortlake to Moorabool 500 kV lines for flow towards Moorabool.

Full details on the limits advice are to be published shortly on the AEMO website: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

The revised limit has been implemented at 1201 hrs on Tuesday 29th April 2025, by updating V^^V_NIL_SWVIC.

For further details on this constraint equation please contact terry.liu@aemo.com.au

Terry Liu
AEMO Operations
     