Market Notices

54565MARKET SYSTEMS20/07/2016 05:27:38 PM

Planned System Maintenance - Gas Supply Hub Production Site Transfer

Change Number: CHG0039839

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Gas Supply Hub

Change Title: Planned System Maintenance - Gas Supply Hub Production Site Transfer

Change Start Date & Time: 26/07/2016 19:00:00 AEST

Change End Date & Time: 26/07/2016 21:00:00 AEST


Outage Start Date & Time: 26/07/2016 19:00:00 AEST

Outage End Date & Time: 26/07/2016 20:00:00 AEST


Change Description:

The Gas Supply Hub Production System is to be transferred to the alternate site to support maintenance activities (QLD to NSW)

Environment: Production

Participant Impact and Requirements:

All access to the Gas Supply Hub (Exchange Trading System) will be unavailable during the outage period. Please access outside this outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54477MARKET SYSTEMS13/07/2016 05:31:01 PM

CHG0039788 UPDATE : Planned System Outage due to maintenance on QLD Internet link (Updated Timeline)

Due to some unforeseen issues, this change was not implemented as planned before on 11th July 2016. Apologies for any inconvenience.

Change Number: CHG0039788

Notification issued to: Market Notice

Notification Type: Update

Change Type: Normal

Service/ Component: Wide Area Network

Change Title: Planned System Outage due to maintenance on QLD Internet link (Updated Timeline)

Change Start Date & Time: 20/07/2016 09:00:00 AEST

Change End Date & Time: 20/07/2016 11:00:00 AEST

Outage Start Date & Time: 20/07/2016 09:00:00 AEST

Outage End Date & Time: 20/07/2016 11:00:00 AEST

Change Description:

The AEMO QLD data center internet telecommunications service will experience an outage as part of an upgraded to this service.

Environment: Production

Participant Impact and Requirements:

Impacts and User Requirements

The following impacts are expected to participant connectivity during this planned outage:

IPWAN Participants - IPWAN Participants - Nil

Lan-2-Lan VPN Participants - Upto 4 x 2 minutes to participants whom have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10)
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.

Remote Access VPN Participants - Upto 4 x 2 minutes to participants who utilise an AEMO RSA token and the AEMO VPN client software to establish their VPN via the AEMO QLD datacenter VPN termination point (202.44.76.8)
Note: Participants are encouraged to establish their VPN client software connections via the alternate AEMO NSW datacenter VPN endpoint (202.44.78.8) prior to this scheduled outage.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54470MARKET SYSTEMS13/07/2016 05:29:47 PM

CHG0039818: Planned System Outage to the Energy Forecasting Web Portal

Change Number: CHG0039818

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Energy Forecasting Web Portal

Change Title: Planned System Outage to the Energy Forecasting Web Portal

Change Start Date & Time: 15/07/2016 09:00:00 AEST

Change End Date & Time: 15/07/2016 13:00:00 AEST

Outage Start Date & Time: 15/07/2016 09:00:00 AEST

Outage End Date & Time: 15/07/2016 12:00:00 AEST


Change Description:

Update of Forecasting Interactive Website (http://forecasting.aemo.com.au) with usability enhancements and support for previous years forecasts.

Environment: Production

Participant Impact and Requirements:

Forecasting Interactive Website and associated Administration Webpage may not be available during the deployment window. Users need to try accessing the website after the deployment is completed as mentioned in the timeline.

Support Information:

Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54469MARKET SYSTEMS13/07/2016 05:29:03 PM

CHG0039787: Planned System Outage - Gas Supply Hub Pre-production

Change Number: CHG0039787

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Gas Supply Hub

Change Title: Planned System Outage - Gas Supply Hub Pre-production

Change Start Date & Time: 14/07/2016 10:00:00 AEST

Change End Date & Time: 14/07/2016 14:00:00 AEST

Outage Start Date & Time: 14/07/2016 10:00:00 AEST

Outage End Date & Time: 14/07/2016 14:00:00 AEST


Change Description:

Maintenance is performed on Gas Supply Hub periodically to improve security, reliability and performance.

Environment: Pre-Production

Participant Impact and Requirements:

All access to the Preproduction Gas Supply Hub (Exchange Trading System) will be unavailable during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
54434RESERVE NOTICE12/07/2016 12:36:35 PM

Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) condition in the South Australia region - STPASA

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 conditions in the South Australia region advised in AEMO Electricity Market Notice No. 54410 are cancelled at 1200 hrs 12/07/2016.

Ashley Dunn
Operations Planning
54410RESERVE NOTICE12/07/2016 04:21:49 AM

FORECAST LACK OF RESERVE LEVEL 2 (LOR2) in the South Australia region (ST PASA).


AEMO ELECTRICITY MARKET NOTICE


FORECAST LACK OF RESERVE LEVEL 2 (LOR2) in the South Australia region (ST PASA).


AEMO declares forecast LOR2 conditions for the South Australia region for the following periods.

Wednesday 13th July 2016 from 1800 hrs to 1830 hrs

The minimum reserve available is 163 MW.

Thursday 14th July 2016 from 1830 hrs to 1930 hrs

The minimum reserve available is 171 MW.

This calculation is based on a LOR2 trigger level of 200 MW.

AEMO is seeking a market response.


Manager NEM Real Time Operations


54321RESERVE NOTICE07/07/2016 07:21:06 PM

Cancellation - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region - PDPASA - 7 Jul 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region - PDPASA - 7 Jul 2016

The Forecast LOR2 condition in the SA Region advised in AEMO Electricity Market Notice No. 54303 is cancelled at 1920 hrs 7 Jul 2016.


Manager NEM Real Time Operations
54303RESERVE NOTICE07/07/2016 05:39:11 PM

Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region - PDPASA - 7 Jul 2016

AEMO ELECTRICITY MARKET NOTICE

Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region - PDPASA - 7 Jul 2016

AEMO declares a Forecast LOR2 condition for the SA Region.

From 1830 hrs to 1930 hrs 7 July 2016

The contingency capacity reserve required is 200 MW

The minimum reserve available is 182 MW

AEMO is seeking a market response.

AEMO is not intending to intervene at this point in time.

Manager NEM Real Time Operations
54296RESERVE NOTICE07/07/2016 04:36:45 PM

Cancellation - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region - PDPASA - 7 Jul 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region - PDPASA - 7 Jul 2016

The Forecast LOR2 condition in the SA Region advised in AEMO Electricity Market Notice No. 54289 is cancelled at 1635 hrs 7 Jul 2016.


Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm