Filter by category
Filter by Date
Cancellation Actual Lack Of Reserve Level 1 (LOR1) in the Qld Region - 12/02/17
Cancellation Actual Lack Of Reserve Level 1 (LOR1) in the Qld Region - 12/02/17
Refer Electricity Market Notice 57472
The Actual LOR1 condition declared for the Qld region is cancelled at 2020 hrs 12/02/2017
Manager NEM Real Time Operations
Cancellation Actual Lack Of Reserve Level 2 (LOR2) in the Qld Region - 12/02/17
Cancellation Actual Lack Of Reserve Level 2 (LOR2) in the Qld Region - 12/02/17
Refer Electricity Market Notice 57473
The Actual LOR2 condition declared for the Qld region is cancelled at 1930 hrs 12/02/2017.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the Qld Region - 12/02/17
Actual Lack Of Reserve Level 2 (LOR2) in the Qld Region - 12/02/17
An Actual LOR2 condition has been declared for the Qld region from 1700 hrs.
The Actual LOR2 condition is forecast to exist until 1800 hrs
The contingency capacity reserve required is 680 MW
The minimum reserve available is 548 MW
AEMO is seeking a market response.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the Qld Region - 12/02/17
Actual Lack Of Reserve Level 1 (LOR1) in the Qld Region - 12/02/17
An Actual LOR1 condition has been declared for the Qld region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs
The contingency capacity reserve required is 1123 MW
The minimum reserve available is 978 MW
Manager NEM Real Time Operations
Cancellation - Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region - 11-02-2017
Cancellation - Actual Lack Of Reserve Level 1 (LOR1 in the NSW Region - 11-02-2017
Refer Electricity Market Notice 57412
The Actual LOR1 declared for the NSW region is cancelled from 1820 hrs.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region - 11-02-2017
Actual Lack Of Reserve Level 1 (LOR1 in the NSW Region - 11-02-2017
An Actual LOR1 condition has been declared for the NSW region from 1210 hrs.
The Actual LOR1 condition is forecast to exist until 1500 hrs
The contingency capacity reserve required is 1330 MW
The minimum reserve available is 803 MW
Manager NEM Real Time Operations
Cancellation - Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region - 10-02-2017
Cancellation - Actual Lack Of Reserve Level 1 (LOR1 in the NSW Region - 10-02-2017
Refer Electricity Market Notice 57402
The Actual LOR1 declared for the NSW region is cancelled from 1930 hrs.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region - 10-02-2017
Actual Lack Of Reserve Level 1 (LOR1 in the NSW Region - 10-02-2017
An Actual LOR1 condition has been declared for the NSW region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs
The contingency capacity reserve required is 1340 MW
The minimum reserve available is 843 MW
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region - 10-02-2017
Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region - 10-02-2017
An Actual LOR2 condition has been declared for the NSW region from 1635 hrs.
The Actual LOR2 condition is forecast to exist until 1730 hrs
The contingency capacity reserve required is 675 MW
The minimum reserve available is 570 MW
AEMO is seeking a market response.
Manager NEM Real Time Operations