NON-CONFORMANCE Region VIC1 Wednesday, 8 June 2016
NON-CONFORMANCE VIC1 Region Wednesday, 8 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS1
Duration: 08/06/2016 18:50 to 08/06/2016 22:05
Amount: 30 MW
Constraint: NC-V_YWPS1
Auto-generated on behalf of Manager NEM Real Time Operations
Changes to raise FCAS requirements in Tasmania
Changes to raise FCAS requirements in Tasmania
Refer to AEMO Electricity market notice 51618
The adaptive under-frequency load shedding scheme (AUFLS) was implemented in January 2016 to reduce the contingency raise FCAS requirements in Tasmania. TasNetworks has advised AEMO this scheme was disabled at 1000 hrs 8 June 2016. Tasmanian contingency FCAS requirements now do not use the reduction provided by this scheme.
Ben Blake
AEMO Operations
NON-CONFORMANCE Region VIC1 Tuesday, 7 June 2016
NON-CONFORMANCE VIC1 Region Tuesday, 7 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS2
Duration: 07/06/2016 13:30 to 07/06/2016 13:40
Amount: 38 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Tuesday, 7 June 2016
NON-CONFORMANCE VIC1 Region Tuesday, 7 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS2
Duration: 07/06/2016 08:00 to 07/06/2016 08:05
Amount: -31 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 6 June 2016
NON-CONFORMANCE NSW1 Region Monday, 6 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: ER02
Duration: 06/06/2016 21:45 to 06/06/2016 21:50
Amount: -66 MW
Constraint: NC-N_ER02
Auto-generated on behalf of Manager NEM Real Time Operations
Constraint Automation to Manage Power Security in Vic Region.
Constraint Automation to Manage Power Security in Vic Region, Monday, 06 June 2016.
AEMO network analysis indicated that the trip of the Hazelwood Power station to Hazelwood Terminal station No.2 220 kV line would result in an overload of the Hazelwood Power station to Hazelwood Terminal station A1 500 / 220 kV transformer.
AEMO invoked automated constraint set CA_SPS_4667C455 from 1850 to 1905 hrs to manage power system security.
Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Monday, 6 June 2016
NON-CONFORMANCE SA1 Region Monday, 6 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: TORRA2
Duration: 06/06/2016 18:25 to 06/06/2016 18:30
Amount: -20 MW
Constraint: NC-S_TORRA2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 6 June 2016
NON-CONFORMANCE NSW1 Region Monday, 6 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: SITHE01
Duration: 06/06/2016 04:35 to 06/06/2016 05:50
Amount: 22 MW
Constraint: NC-N_SITHE01
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 5 June 2016
NON-CONFORMANCE NSW1 Region Sunday, 5 June 2016
AEMO declared a schedule generating unit non-conforming
Unit: URANQ14
Duration: 05/06/2016 09:55 to 05/06/2016 10:05
Amount: -102 MW
Constraint: NC-N_URANQ14
Auto-generated on behalf of Manager NEM Real Time Operations