Update Inter-Regional Transfer limit variation - Basslink 21/05/2024
Update Inter-Regional Transfer limit variation - Basslink
Refer AEMO Electricity Market Notice 116734
There was an unplanned outage of the Basslink interconnector at 0235 hrs. The Basslink interconnector has been returned to service.
The following constraint set was revoked at 0810 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Basslink 21/05/2024
Inter-Regional Transfer limit variation - Basslink
There has been an unplanned outage of the Basslink interconnector at 0235 hrs
The following constraint set was invoked at 0240 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
[EventId:202405191520_confirmed] Prices for interval 19-May-2024 15:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024
PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:20.
In accordance with Market Notice 116704 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405191545_confirmed] Prices for interval 19-May-2024 15:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024
PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:45.
In accordance with Market Notice 116709 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405191540_confirmed] Prices for interval 19-May-2024 15:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024
PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:40.
In accordance with Market Notice 116708 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405191535_confirmed] Prices for interval 19-May-2024 15:35 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024
PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:35.
In accordance with Market Notice 116707 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405191530_confirmed] Prices for interval 19-May-2024 15:30 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024
PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:30.
In accordance with Market Notice 116706 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:202405191525_confirmed] Prices for interval 19-May-2024 15:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1545 hrs on 19 May 2024
PRICES ARE NOW CONFIRMED for trading interval 19-May-2024 15:25.
In accordance with Market Notice 116705 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Cancellation of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Cancellation time: 18/05/2024 20:09
Constraint set(s) revoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Refer AEMO Electricity Market Notice 116690
Auto-generated on behalf of Manager NEM Real Time Operations