Market Notices

55339MARKET INTERVENTION11/10/2016 05:05:04 PM

Direction - South Australia region 11/10/16

AEMO ELECTRICITY MARKET NOTICE.

Direction - South Australia region 11/10/16

In accordance with clause 4.8.9 of the National Electricity Rules AEMO has issued a direction to a participant in the South Australia region.

The direction was necessary to maintain the power system in a secure operating state.

The direction was issued at 1616 hrs 11/10/16 and is expected to stay in place until 0700 hrs 12/10/16.

Manager NEM Real Time Operations
55337MARKET INTERVENTION11/10/2016 04:12:03 PM

Forecast Intervention Event - South Australia region 11 and 12 October 2016

AEMO ELECTRICITY MARKET NOTICE

Forecast Intervention Event - South Australia region 11 and 12 October 2016

Predispatch is indicating a power system security violation in the South Australia region between 2100 hrs 11/10/16 and 1400hrs 12/10/16.

AEMO is seeking a market response from synchronous generating units in the South Australia region with an installed capacity of greater than 100 MW.

AEMO will determine the latest time at which it would need to intervene through a AEMO intervention event.

Manager NEM Real Time Operations
55334MARKET INTERVENTION11/10/2016 01:05:05 PM

Forecast Intervention Event - South Australia region 12/10/16

AEMO ELECTRICITY MARKET NOTICE

Forecast Intervention Event - South Australia region 12/10/16

Predispatch is indicating a power system security violation in the South Australia region between 0000 hrs and 1400hrs Wednesday 12 October 2016.

AEMO is seeking a market response from synchronous generating units in the South Australia region with an installed capacity of greater than 100 MW.

AEMO will determine the latest time at which it would need to intervene through a AEMO intervention event.

Manager NEM Real Time Operations
55308MARKET INTERVENTION10/10/2016 05:32:49 AM

Cancellation - Direction - South Australia region

Cancellation - Direction - South Australia region

Refer AEMO Electricity Market Notice 55293

The direction was issued at 2054 hrs 09/10/16 and cancelled at 0530 hrs 10/10/16.

Manager NEM Real Time Operations
55294MARKET INTERVENTION09/10/2016 10:04:11 PM

Direction - South Australia region - Intervention Pricing

AEMO ELECTRICITY MARKET NOTICE.

Refer AEMO Electricity Market Notice no. 55293.

An AEMO Intervention Event has been implemented by issuing a direction to maintain the power system in a secure operating state.

AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.

The AEMO Intervention Event will commence in the 0000 hrs 10/10/16 dispatch interval and is forecast to apply until 0530 hrs 10/10/16

Intervention pricing will not be implemented from the 0000 hrs 10/10/16 dispatch interval until the end of the AEMO Intervention Event.

Manager NEM Real Time Operations
55293MARKET INTERVENTION09/10/2016 10:01:34 PM

Direction - South Australia region

AEMO ELECTRICITY MARKET NOTICE.

Direction - South Australia region

In accordance with clause 4.8.9 of the National Electricity Rules AEMO has issued a direction to a participant in the South Australia region.

The direction was necessary to maintain the power system in a secure operating state.

The direction was issued at 2054 hrs and is expected to stay in place until 0530 hrs 10/10/16

Manager NEM Real Time Operations
54877ADMINISTERED PRICE CAP09/09/2016 03:55:07 AM

[EventId:92] AP ENDED for market ancillary services in SA at 09 September 2016 04:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0355 hrs on 9 September 2016

ADMINISTERED PRICE PERIOD ENDS in SA region.

In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market particpants that the administered price period declared for the SA region in market notice 54863 will end at 0400 hrs on 9 September 2016.


This is an AEMO autogenerated Market Notice.
54865RESERVE NOTICE12/09/2016 09:24:16 AM

Forecast Lack Of Reserve Level 2 (LOR2) in South Australia Region - 13, 14 and 16 Sep 2016

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Market Notices: 54734, 54735 and 54864.

Forecast Lack Of Reserve Level 2 (LOR2) in South Australia Region for the following periods:

On 13/09/2016 from 0700 hrs to 1700 hrs;
On 14/09/2016 from 0700 hrs to 1700 hrs; and
On 16/09/2016 from 0700 hrs to 1700 hrs.

AEMO declares Forecast LOR2 conditions in the South Australia region for the above periods. During these periods, outages are scheduled for Moorabool to Mortlake No.2 500 kV transmission line in Victoria region.

On the occurrence of a credible contingency during these outages, South Australia region could separate from the rest of the NEM and is likely to result in interruptions to power supplies in South Australia.

There are sufficient capacity reserves in the South Australia region to meet electricity demand but following the next credible contingency it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing interruptions to power supplies in South Australia.

Harmohan Singh
Operations Planning
54863ADMINISTERED PRICE CAP08/09/2016 03:55:30 AM

[EventId:92] AP STARTED for market ancillary services in SA at 08 September 2016 04:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0355 hrs on 8 September 2016

ADMINISTERED PRICE PERIOD DECLARED in SA region.

AEMO has determined that the rolling sum of the uncapped market ancillary Lower Reg, Raise Reg services(s) prices for the SA region over the previous 2016 dispatch intervals has exceeded 6 times the cumulative price threshold (CPT) of $210,100.00.

In accordance with Clause 3.14 of the National Electricity Rules, AEMO has determined that an administered price period will commence at the dispatch interval starting 0400 hrs on 8 Sep 2016 and will continue through to the end of that trading day.

An administered price cap (APC) of 300 $/MWh will apply to all dispatch intervals during this administered price period. This APC will apply to all market ancillary service prices in the SA region.

An administered floor price (AFP) of 0 $/MWh AFP will apply to all market ancillary service prices.

AEMO will continue to monitor the rolling sum of the uncapped market ancillary service prices and issue further market notices as required.


This is an AEMO autogenerated Market Notice.