Filter by category
Filter by Date
CHG0038803 - Planned System Change - MSATS Pre-Production Mid-Year 2016 - Release 46.85
Change Number: CHG0038803
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution
Change Title: Planned System Change - MSATS Pre-Production Mid-Year 2016 - Release 46.85
Change Description:
Implementation has been completed with no issues.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0039217 - Planned System Outage - QLD MarketNet VPN POP
Change Number: CHG0039217
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Network
Change Title: Planned System Outage - QLD MarketNet VPN POP
Change Start Date & Time: 08/06/2016 10:00:00 AEST
Change End Date & Time: 08/06/2016 12:00:00 AEST
Outage Start Date & Time: 08/06/2016 10:00:00 AEST
Outage End Date & Time: 08/06/2016 12:00:00 AEST
Change Description:
All MarketNet VPN access via the QLD VPN POP will be impacted.
Environment: Production
Participant Impact and Requirements:
All MarketNet VPN access via the QLD VPN POP will be impacted.
Participants are advised to transition to AEMO's NSW VPN POP during this outage window to minimize any potential outages.
-Site-to-Site: 202.44.78.10 or
-Remote Access: 202.44.78.8
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0039137 - Planned Maintenance to MSATS Production System
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Market Settlement and Transfer Solution (MSATS)
Change Title: Planned Maintenance to MSATS Production System
Change Start Date & Time: 10/06/2016 18:30:00 AEST
Change End Date & Time: 10/06/2016 19:30:00 AEST
Outage Start Date & Time: 10/06/2016 18:30:00 AEST
Outage End Date & Time: 10/06/2016 19:30:00 AEST
Change Description:
This is a maintenance to MSATS Production Batch Handlers to fulfill a request by one of the registered participants.
Environment: Production
Participant Impact and Requirements:
Awareness of this Change. Participants will still be able to send files, these files will be queued for 5 to 10 minutes and processed after the change implementation.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NON-CONFORMANCE Region QLD1 Tuesday, 31 May 2016
NON-CONFORMANCE QLD1 Region Tuesday, 31 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: BRAEMAR3
Duration: 31/05/2016 17:45 to 31/05/2016 17:55
Amount: 9 MW
Constraint: NC-Q_BRAEMAR3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Tuesday, 31 May 2016
NON-CONFORMANCE VIC1 Region Tuesday, 31 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: HWPS7
Duration: 31/05/2016 16:00 to 31/05/2016 16:05
Amount: -54 MW
Constraint: NC-V_HWPS7
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Tuesday, 31 May 2016
NON-CONFORMANCE NSW1 Region Tuesday, 31 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: MP2
Duration: 31/05/2016 11:40 to 31/05/2016 11:55
Amount: -31 MW
Constraint: NC-N_MP2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 31 May 2016
NON-CONFORMANCE QLD1 Region Tuesday, 31 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: BRAEMAR2
Duration: 31/05/2016 07:30 to 31/05/2016 07:45
Amount: -13 MW
Constraint: NC-Q_BRAEMAR2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Tuesday, 31 May 2016
NON-CONFORMANCE QLD1 Region Tuesday, 31 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: BRAEMAR1
Duration: 31/05/2016 07:15 to 31/05/2016 07:45
Amount: -13 MW
Constraint: NC-Q_BRAEMAR1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Tuesday, 31 May 2016
NON-CONFORMANCE VIC1 Region Tuesday, 31 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: HWPS3
Duration: 31/05/2016 00:45 to 31/05/2016 00:50
Amount: 10 MW
Constraint: NC-V_HWPS3
Auto-generated on behalf of Manager NEM Real Time Operations