58480RESERVE NOTICE04/05/2017 05:06:02 PM

STPASA - Update of the Forecast Lack of Reserve Level 2 (LOR2) in the Victoria Region on 10 and 11 May 2017

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the Vic region advised in AEMO Electricity Market Notice No. 58475 has been updated at 1600 hrs 04/05/2017 to the following:

1. From 1730 hrs to 1900 hrs on 10/05/2017.
The contingency capacity reserve required is 594 MW.
The minimum reserve available is 519 MW.

2. From 0700 hrs to 1030 hrs on 11/05/2017.
The contingency capacity reserve required is 594 MW.
The minimum reserve available is 311 MW.

3. From 1330 hrs to 2030 hrs on 11/05/2017.
The contingency capacity reserve required is 594 MW.
The minimum reserve available is 0 MW.

AEMO is seeking a market response.

AEMO will determine the latest time at which they would need to intervene through an AEMO intervention event.

Daniel Ghantous
AEMO Operations
58479RESERVE NOTICE04/05/2017 05:05:45 PM

STPASA - Update of the Forecast Lack of Reserve Level 2 (LOR2) in the SA Region on 11/05/2017

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 58476 has been updated at 1600 hrs 04/05/2017 to the following:

1. From 0800 hrs to 0830 hrs on 11/05/2017.
The contingency capacity reserve required is 350 MW.
The minimum reserve available is 311 MW.

2. From 1730 hrs to 1800 hrs on 11/05/2017.
The contingency capacity reserve required is 350 MW.
The minimum reserve available is 2 MW.

AEMO is seeking a market response.

AEMO will determine the latest time at which they would need to intervene through an AEMO intervention event.

Daniel Ghantous
AEMO Operations
58476RESERVE NOTICE04/05/2017 03:18:15 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 11/05/2017

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(c) of the National Electricity Rules for the SA region for the following period:

From 1730 hrs to 1800 hrs on 11/05/2017.
The contingency capacity reserve required is 350 MW.
The minimum reserve available is 111 MW.

AEMO is seeking a market response.

AEMO will determine the latest time at which they would need to intervene through an AEMO intervention event.

Daniel Ghantous
AEMO Operations
58475RESERVE NOTICE04/05/2017 03:17:58 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the Victoria Region on 10 and 11 May 2017

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(c) of the National Electricity Rules for the VIC region for the following periods:

1. From 1730 hrs to 1900 hrs on 10/05/2017.
The contingency capacity reserve required is 594 MW.
The minimum reserve available is 506 MW.

2. From 0700 hrs to 1030 hrs on 11/05/2017.
The contingency capacity reserve required is 594 MW.
The minimum reserve available is 357 MW.

3. From 1400 hrs to 1600 hrs on 11/05/2017.
The contingency capacity reserve required is 594 MW.
The minimum reserve available is 512 MW.

4. From 1630 hrs to 2000 hrs on 11/05/2017.
The contingency capacity reserve required is 594 MW.
The minimum reserve available is 0 MW.

AEMO is seeking a market response.

AEMO will determine the latest time at which they would need to intervene through an AEMO intervention event.

Daniel Ghantous
AEMO Operations
58451MARKET INTERVENTION26/04/2017 12:22:01 PM

Cancellation - Direction - South Australia region 26/04/17

AEMO ELECTRICITY MARKET NOTICE.

Cancellation - Direction - South Australia region 26/04/17

Update to AEMO Electricity Market Notice 58432, 58439, 58441, 58447 and 58450

The AEMO Intervention Event concluded in the Dispatch Interval 1210 hrs 26/04/17

AEMO issued 2 directions to participants in the South Australia region in accordance with section 116 of the National Electricity Law.
Direction 1 from 0234 hrs 25/04/17 to 1415 hrs 25/04/17 (see MN 58432)
Direction 2 from 0745 hrs 25/04/17 to 1207 hrs 26/04/17 (see MN 58439)

To minimise the effect on interconnector flows and minimise the number of Affected Participants in accordance with clause 4.8.9(h) of the National Electricity Rules, AEMO applied two constraints to generating units in the South Australia region

Counter Action 1 from 0950 hrs 25/04/17 to 1430 hrs 25/04/17
Counter Action 2 from 1550 hrs 25/04/17 to 1210 hrs 26/04/17


Manager NEM Real Time Operations
58450MARKET INTERVENTION26/04/2017 07:16:03 AM

Update - Direction - South Australia region 26/04/17

AEMO ELECTRICITY MARKET NOTICE.

Update - Direction - South Australia region 26/04/17

Update to AEMO Electricity Market Notice 58439, 58441 and 58447

The AEMO Intervention Event commenced in the 0750 hrs dispatch interval 25/04/17and is forecast to apply until 1200 hrs 26/04/17

Intervention pricing will be implemented during the AEMO Intervention Event.


Manager NEM Real Time Operations
58447MARKET INTERVENTION25/04/2017 04:58:48 PM

Update - Direction - South Australia region 25/04/17

AEMO ELECTRICITY MARKET NOTICE.

Update - Direction - South Australia region 25/04/17

Update to AEMO Electricity Market Notice 58439 and 58441

The AEMO Intervention Event commenced in the 0750 hrs dispatch interval 25/04/17and is forecast to apply until 0900 hrs 26/04/17

Intervention pricing will be implemented during the AEMO Intervention Event.


Manager NEM Real Time Operations
58445MARKET INTERVENTION25/04/2017 02:31:56 PM

Update - Direction - South Australia region - 25/04/17

AEMO ELECTRICITY MARKET NOTICE.

Refer to AEMO Electricity Market Notice No. 58442

From 0950 hrs to 1430 hrs AEMO applied a constraint to a generating unit in the South Australia region to minimise the effect on interconnector flows and minimise the number of Affected Participants in accordance with clause 4.8.9(h) of the National Electricity Rules.

Manager NEM Real Time Operations
58442MARKET INTERVENTION25/04/2017 09:54:49 AM

Update - Direction - South Australia region - 25/04/17

AEMO ELECTRICITY MARKET NOTICE.

Refer to AEMO Electricity Market Notice No. 58439

At 0950 hrs, AEMO applied a constraint to a generating unit in the South Australia region to minimise the effect on interconnector flows and minimise the number of Affected Participants in accordance with clause 4.8.9(h) of the National Electricity Rules.