CHG0041931 - Planned System Outage - QLD Internet link maintenance
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Internet
Change Title: Planned System Outage - QLD Internet link maintenance
Change Start Date & Time: 07/02/2017 09:00:00 AEST
Change End Date & Time: 07/02/2017 11:00:00 AEST
Outage Start Date & Time: 07/02/2017 09:00:00 AEST
Outage End Date & Time: 07/02/2017 11:00:00 AEST
Change Description:
The AEMO QLD data center internet telecommunications service will experience an outage as part of an upgrade to this service.
Environment: Production
Participant Impact and Requirements:
The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants - Upto 1 x 10 minutes to participants whom have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10)
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.
Remote Access VPN Participants - Upto 1 x 10 minutes to participants who utilise an AEMO RSA token and the AEMO VPN client software to establish their VPN via the AEMO QLD datacenter VPN termination point (202.44.76.8)
Note: Participants are encouraged to establish their VPN client software connections via the alternate AEMO NSW datacenter VPN endpoint (202.44.78.8) prior to this scheduled outage.
SSLVPN VPN Participants - Nil impacts to participants who utilise an AEMO RSA token and the AEMO SSLVPN client software to establish their VPN via the URL marketnetvpn.aemo.com.au
CHG0041820 : Planned System Maintenance to MSATS Pre-Production Completed
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution
Change Title: Planned System Maintenance to MSATS Pre-Production
Change Description:
Implemented and verified successfully.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0041820 - Planned System Maintenance to MSATS Pre-Production
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution
Change Title: Planned System Maintenance to MSATS Pre-Production
Change Start Date & Time: 18/01/2017 10:00:00 AEST
Change End Date & Time: 18/01/2017 12:00:00 AEST
Outage Start Date & Time: 18/01/2017 10:00:00 AEST
Outage End Date & Time: 18/01/2017 12:00:00 AEST
Change Description:
Maintenance on Market Settlement and Transfer Solutions (MSATS) to increase reliability, stability and security.
Environment: Pre-Production
Participant Impact and Requirements:
No action required. Access to all parts of the production Electricity MSATS system will not be available during the outage period. Access should be attempted outside the specified outage times.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0041884 - Planned System Maintenance to MSATS Production
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution
Change Title: Planned System Maintenance to MSATS Production
Change Start Date & Time: 25/01/2017 17:30:00 AEST
Change End Date & Time: 25/01/2017 19:30:00 AEST
Outage Start Date & Time: 25/01/2017 17:30:00 AEST
Outage End Date & Time: 25/01/2017 19:30:00 AEST
Change Description:
Maintenance on Market Settlement and Transfer Solutions (MSATS) to increase reliability, stability and security.
Environment: Production
Participant Impact and Requirements:
No action required. Access to all parts of the production Electricity MSATS system will not be available during the outage period. Access should be attempted outside the specified outage times.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0041689: Planned System Outage to OPDMS to deploy new version to Production environment
Change Number: CHG0041689
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Operations and Planning Data Management
Change Title: Planned System Outage to OPDMS to deploy new version to Production environment
Change Start Date & Time: 18/01/2017 10:00:00 AEST
Change End Date & Time: 18/01/2017 12:00:00 AEST
Outage Start Date & Time: 18/01/2017 10:00:00 AEST
Outage End Date & Time: 18/01/2017 12:00:00 AEST
Change Description:
Deploy new version of OPDMS (7.11.0) to Production environment
Enhancements:
* Support for PSSE v34 dynamics snapshots for internal and TNSP planners and modellers
* New droop feature
* MBASE correction feature
Environment: Production
Participant Impact and Requirements:
All OPDMS Production users must log out of OPDMS prior to outage period. OPDMS will be unavailable during outage. New client software components will be downloaded and installed automatically on next OPDMS client session.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0041732: Planned System Maintenance - EMMS Pre-production
Change Number: CHG0041732
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Planned System Maintenance - EMMS Pre-production
Change Start Date & Time: 11/01/2017 09:00:00 AEST
Change End Date & Time: 11/01/2017 18:00:00 AEST
Outage Start Date & Time: 11/01/2017 09:00:00 AEST
Outage End Date & Time: 11/01/2017 18:00:00 AEST
Change Description:
Maintenance is performed on the EMMS Preproduction to improve reliability and performance.
Environment: Pre-Production
Participant Impact and Requirements:
Awareness of this maintenance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0041722 : Planned System Outage - MSATS & EMMS Pre-production - Completed
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution
Change Title: Planned System Outage - MSATS & EMMS Pre-production
Change Description:
Completed Successfully. MSATS & EMMS Pre-production is available for use.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0041722 : Planned System Outage - MSATS & EMMS Pre-production
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution
Change Title: Planned System Outage - MSATS & EMMS Pre-production
Change Start Date & Time: 22/12/2016 10:00:00 AEST
Change End Date & Time: 22/12/2016 16:00:00 AEST
Outage Start Date & Time: 22/12/2016 10:00:00 AEST
Outage End Date & Time: 22/12/2016 16:00:00 AEST
Change Description:
Maintenance on Market Settlement and Transfer Solutions (MSATS) and EMMS to increase reliability, stability and security.
Environment: Pre-Production
Participant Impact and Requirements:
No action required. Access to all parts of the pre-production EMMS and Electricity MSATS system will not be available during the outage period. Access should be attempted outside the specified outage times.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0041706 : Planned System Maintenance - Electricity MMS PreProduction Bay Transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Planned System Maintenance - Electricity MMS PreProduction Bay Transfer
Change Start Date & Time: 21/12/2016 11:00:00 AEST
Change End Date & Time: 21/12/2016 16:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Change Description:
The transfer is not expected to have any impact, however, participants are reminded that this activity is not without risk and therefore if an electricity market system issue is identified after the transfer it should be reported to AEMO
Environment: Pre-Production
Participant Impact and Requirements:
The transfer is not expected to have any impact, however, participants are reminded that this activity is not without risk and therefore if an electricity market system issue is identified after the transfer it should be reported to AEMO
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.