[EventId:77] AP ENDED for market ancillary services in SA at 12 August 2016 04:00
Issued by Australian Energy Market Operator Ltd at 0355 hrs on 12 August 2016
ADMINISTERED PRICE PERIOD ENDS in SA region.
In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO is notifying market particpants that the administered price period declared for the SA region in market notice 54699 will end at 0400 hrs on 12 August 2016.
This is an AEMO autogenerated Market Notice.
[EventId:77] AP STARTED for market ancillary services in SA at 11 August 2016 19:25
Issued by Australian Energy Market Operator Ltd at 1920 hrs on 11 August 2016
ADMINISTERED PRICE PERIOD DECLARED in SA region.
AEMO has determined that the rolling sum of the uncapped market ancillary Lower Reg services(s) prices for the SA region over the previous 2016 dispatch intervals has exceeded 6 times the cumulative price threshold (CPT) of $210,100.00.
In accordance with Clause 3.14 of the National Electricity Rules, AEMO has determined that an administered price period will commence at the dispatch interval starting 1925 hrs on 11 Aug 2016 and will continue through to the end of that trading day.
An administered price cap (APC) of 300 $/MWh will apply to all dispatch intervals during this administered price period. This APC will apply to all market ancillary service prices in the SA region.
An administered floor price (AFP) of 0 $/MWh AFP will apply to all market ancillary service prices.
AEMO will continue to monitor the rolling sum of the uncapped market ancillary service prices and issue further market notices as required.
This is an AEMO autogenerated Market Notice.
Planned outage of Heywood No.2 500kV Bus in Victoria region from 06/09/2016 0700 hrs to 09/09/2016 1700 hrs
This market notice is FOR INFORMATION ONLY.
The Heywood No.2 500 kV busbar in Victoria Region is planned out of service from 0700 hrs on 6 September 2016 to 1700 hrs on 9 September 2016. During this outage, Heywood 500/275 kV M2 transformer will be off-loaded and Heywood - Mortlake - Alcoa Portland No.2 500 kV line will be opened at Heywood.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-I_HYSE (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-HYTX_M12
V-HY_500BUS
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 02/09/2016 0700 hrs to 02/09/2016 1700 hrs
This market notice is FOR INFORMATION ONLY.
The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0700 hrs on 2 September 2016 to 1700 hrs on 2 September 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 31/08/2016 0700 hrs to 31/08/2016 1700 hrs
Update to MN 54682 - Subject updated accordingly. Content of the market notice didn't change.
This market notice is FOR INFORMATION ONLY.
The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0700 hrs on 31 August 2016 to 1700 hrs on 31 August 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 01/09/2016 0700 hrs to 01/09/2016 1700 hrs
This market notice is FOR INFORMATION ONLY.
The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0700 hrs on 1 September 2016 to 1700 hrs on 1 September 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 20/08/2016 0630 hrs to 20/08/2016 1800 hrs
This market notice is FOR INFORMATION ONLY.
The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0700 hrs on 31 August 2016 to 1700 hrs on 31 August 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Cancellation - Evacuation of Brisbane Control Centre Wednesday, 3 August 2016 Refer AEMO Electricity Market Notice 54655
Cancellation - Evacuation of Brisbane Control Centre Wednesday, 3 August 2016 Refer AEMO Electricity Market Notice 54655
AEMO advises all participants that AEMO Brisbane Control centre has resumed normal operation from 1125 hrs. Wednesday, 3 August 2016
Manager NEM Real Time Operations
Emergency Exercise - Evacuation of Brisbane Control Centre Wednesday, 3 August 2016
Emergency Exercise - Evacuation of Brisbane Control Centre Wednesday, 3 August 2016
AEMO advises all participants that AEMO Brisbane Control centre has been evacuated from 1057 hrs 03/08/16 until further notice. Please direct all operational enquiries to the Sydney Control Centre.
Manager NEM Real Time Operations