Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 31/08/2016 0700 hrs to 31/08/2016 1700 hrs
Update to MN 54682 - Subject updated accordingly. Content of the market notice didn't change.
This market notice is FOR INFORMATION ONLY.
The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0700 hrs on 31 August 2016 to 1700 hrs on 31 August 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 01/09/2016 0700 hrs to 01/09/2016 1700 hrs
This market notice is FOR INFORMATION ONLY.
The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0700 hrs on 1 September 2016 to 1700 hrs on 1 September 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 20/08/2016 0630 hrs to 20/08/2016 1800 hrs
This market notice is FOR INFORMATION ONLY.
The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0700 hrs on 31 August 2016 to 1700 hrs on 31 August 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Edmund Hon
AEMO Operations
Cancellation - Evacuation of Brisbane Control Centre Wednesday, 3 August 2016 Refer AEMO Electricity Market Notice 54655
Cancellation - Evacuation of Brisbane Control Centre Wednesday, 3 August 2016 Refer AEMO Electricity Market Notice 54655
AEMO advises all participants that AEMO Brisbane Control centre has resumed normal operation from 1125 hrs. Wednesday, 3 August 2016
Manager NEM Real Time Operations
Emergency Exercise - Evacuation of Brisbane Control Centre Wednesday, 3 August 2016
Emergency Exercise - Evacuation of Brisbane Control Centre Wednesday, 3 August 2016
AEMO advises all participants that AEMO Brisbane Control centre has been evacuated from 1057 hrs 03/08/16 until further notice. Please direct all operational enquiries to the Sydney Control Centre.
Manager NEM Real Time Operations
Planned outage of Moorabool to Mortlake PS 500kV line in Victoria region from 28/08/2016 0630 hrs to 28/08/2016 1800 hrs
This market notice is FOR INFORMATION ONLY.
The Moorabool to Mortlake PS 500kV line in Victoria Region is planned out of service from 0630 hrs on 28 August 2016 to 1800 hrs on 28 August 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLMO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Operations Planning
Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 27/08/2016 0630 hrs to 27/08/2016 1800 hrs
This market notice is FOR INFORMATION ONLY.
The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0630 hrs on 27 August 2016 to 1800 hrs on 27 August 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Operations Planning
Planned outage of Moorabool to Mortlake PS 500kV line in Victoria region from 21/08/2016 0630 hrs to 21/08/2016 1800 hrs
This market notice is FOR INFORMATION ONLY.
The Moorabool to Mortlake PS 500kV line in Victoria Region is planned out of service from 0630 hrs on 21 August 2016 to 1800 hrs on 21 August 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V-MLMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLMO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Operations Planning
Planned outage of Moorabool to Tarrone 500kV line in Victoria region from 20/08/2016 0630 hrs to 20/08/2016 1800 hrs
This market notice is FOR INFORMATION ONLY.
The Moorabool to Tarrone 500kV line in Victoria Region is planned out of service from 0630 hrs on 20 August 2016 to 1800 hrs on 20 August 2016.
During this outage, a credible contingency can separate South Australia region from the rest of the NEM.
Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.
The following constraint sets have been invoked for this outage:
F-V_MLTR (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLTR
V-MACARTHUR_ZERO
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO will continue monitoring this proposed outage and will update the Market accordingly.
Operations Planning