57277RESERVE NOTICE08/02/2017 04:13:52 PM

Actual Lack Of Reserve Level 1 (LOR1) in the SA Region.

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the SA Region.

An Actual LOR1 condition has been declared for the SA Region.

From 1600 hrs to 1900 hrs 08/02/2017

The contingency capacity reserve required is 400 MW

The minimum reserve available is 236 MW


Manager NEM Real Time Operations
57241RESERVE NOTICE06/02/2017 04:50:01 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region.

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region.

Refer AEMO Electricity market notice 57238

An Actual LOR1 condition has been declared for the NSW Region.

From 1330 hrs to 1730 hrs Monday, 6 February 2017

The contingency capacity reserve required is 1340 MW

The minimum reserve available is 768 MW


Manager NEM Real Time Operations

57238RESERVE NOTICE06/02/2017 01:46:45 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region.

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region.

An Actual LOR1 condition has been declared for the NSW Region.

From 1330 hrs to 1700 hrs Monday, 6 February 2017

The contingency capacity reserve required is 1330 MW

The minimum reserve available is 1010 MW


Manager NEM Real Time Operations


56661RESERVE NOTICE06/01/2017 05:44:39 PM

Cancellation of Actual (LOR1) condition in the South Australia region - 6/1/17

AEMO ELECTRICITY MARKET NOTICE
Correction to Market notice 56660 - should be type Market notice type Reserve Notice.

Cancellation of Actual (LOR1) condition in the South Australia region - 6/1/17
The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice No.56660 is cancelled at 1745 hrs 6/1/17.

Manager NEM Real Time Operations
56067MARKET INTERVENTION01/12/2016 03:45:17 PM

Direction ceased - Victoria Region region 1/12/16

AEMO ELECTRICITY MARKET NOTICE.

Direction - Victoria Region region 1/12/16
In accordance with clause 4.8.9 of the National Electricity Rules AEMO has issued a direction to a participant in the Victoria region.
The direction was necessary to re-establish the power system to a secure operating state,
The direction was issued at 1030 hrs and ceased at 1545hrs /1/2/16

Manager NEM Real Time Operations
56060MARKET INTERVENTION01/12/2016 11:15:53 AM

AEMO Intervention Event intervention price dispatch intervals - 1/12/16

AEMO ELECTRICITY MARKET NOTICE.

AEMO Intervention Event intervention price dispatch intervals - 1/12/16
Refer AEMO Electricity Market Notice no. 56046
An AEMO Intervention Event has been implemented by issuing a direction to re-establish the power system to a secure operating state.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
The AEMO Intervention Event commenced in the 1035 hrs dispatch interval.

Intervention pricing will not be implemented during these intervention price dispatch intervals.

Manager NEM Real Time Operations
56046MARKET INTERVENTION01/12/2016 10:59:08 AM

Direction - Victoria Region region 1/12/16

AEMO ELECTRICITY MARKET NOTICE.

Direction - Victoria Region region 1/12/16
In accordance with clause 4.8.9 of the National Electricity Rules AEMO has issued a direction to a participant in the Victoria region.
The direction was necessary to re-establish the power system to a secure operating state,
The direction was issued at 1030 hrs and is expected to stay in place until further notice

Manager NEM Real Time Operations

56022MARKET INTERVENTION01/12/2016 07:42:37 AM

AEMO Intervention Event intervention price dispatch intervals - 1/12/16

AEMO ELECTRICITY MARKET NOTICE.

AEMO Intervention Event intervention price dispatch intervals - 1/12/16
Refer AEMO Electricity Market Notice no. 55973 and 56015
An AEMO Intervention Event has been implemented by issuing a direction to maintain the power system in a secure operating state.
AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.
The AEMO Intervention Event commenced in the 0135 hrs dispatch interval.
Intervention pricing will be implemented during these intervention price dispatch intervals from the 0135 hrs dispatch interval until the end of the AEMO Intervention Event at 0500 hrs 1/12/16

Manager NEM Real Time Operations

56015MARKET INTERVENTION01/12/2016 05:02:31 AM

Cancellation of Directions - South Australia region 01/12/2016

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of Directions - South Australia region 01/12/2016

In accordance with clause 4.8.9 of the National Electricity Rules AEMO had issued directions to participants in the South Australia region.

The directions were necessary to maintain the power system in a secure operating state.

The directions are no longer required and have been cancelled from 0500 hrs 01/12/2016

Manager NEM Real Time Operations