Market Notices

127452MARKET INTERVENTION07/06/2025 04:28:37 PM

Cancellation - AEMO Intervention Event - SA region 06/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 06/06/2025

Refer to Market Notice 127412

The AEMO Intervention Event and all associated directions are cancelled from 1630 hrs on 07/06/2025.


Manager NEM Real Time Operations
     
127451MARKET INTERVENTION07/06/2025 04:28:25 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127440

Direction is cancelled from: 1630 hrs 07/06/2025

Manager NEM Real Time Operations
     
127449INTER-REGIONAL TRANSFER07/06/2025 12:06:39 PM

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

Refer AEMO Electricity Market Notice 127439

AEMO has been notified that the controls to vary Murraylink output are now available.

Constraint set I-CTRL_ISSUE_ML revoked at 1150 hrs.

Manager NEM Real Time Operations
     
127448INTER-REGIONAL TRANSFER07/06/2025 12:06:34 PM

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

AEMO ELECTRICITY MARKET NOTICE

Cancellation Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region).

Refer AEMO Electricity Market Notice 127438

AEMO has been notified that the controls to vary Directlink output are now available.

Constraint set I-CTRL_ISSUE_TE revoked at 1150 hrs.

Manager NEM Real Time Operations
     
127442MARKET INTERVENTION07/06/2025 09:19:00 AM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 2230 hrs 07/06/2025.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
127440MARKET INTERVENTION07/06/2025 09:17:49 AM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127413

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 07/06/2025.

The direction update is issued at 0915 hrs 07/06/2025.

Manager NEM Real Time Operations
     
127439INTER-REGIONAL TRANSFER07/06/2025 09:21:20 AM

Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Murraylink control unavailable (SA Region)

AEMO has been notified that the controls to vary Murraylink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_ML invoked from 0920 hrs.

The constraint set contains equations with the following interconnector on the LHS:

V-S-MNSP1


Manager NEM Real Time Operations
     
127438INTER-REGIONAL TRANSFER07/06/2025 08:58:31 AM

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer limit variation - Directlink control unavailable (NSW Region)

AEMO has been notified that the controls to vary Directlink output are unavailable until further notice.

Constraint set I-CTRL_ISSUE_TE invoked from 0855 hrs.

The constraint set contains equations with the following interconnector on the LHS:

N-Q-MNSP1


Manager NEM Real Time Operations
     
127413MARKET INTERVENTION06/06/2025 04:29:10 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 127412


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1630 hrs 06/06/2025
Type of resource: generating unit
Required actions: Remain synchronised and follow dispatch targets at 1900 hrs 06/06/2025
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: The synchronous generating units currently expected to be synchronised in SA will be inadequate to maintain sufficient Voltage Control in SA. Intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/06/2025.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm