Market Notices

55418RESERVE NOTICE18/10/2016 05:51:15 PM

Actual LOR2 South Australia Region - 18 October 2016

AEMO ELECTRICITY MARKET NOTICE

Actual LOR2 South Australia Region - 18 October 2016
Refer AEMO Electricity Market Notice 55389
An actual LOR2 condition has been declared for the South Australia region from 1745 hrs and is forecast to continue until further notice during a planned outage of Heywood to South East No.2 275 kV transmission line between the Victoria and South Australia regions.

If a credible contingency event occurs in this period the South Australia region would separate from the rest of the NEM and is likely to result in interruptions to power supplies.

There are sufficient capacity reserves in the South Australia region to meet electricity demand but it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing power interruptions.

Manager NEM Real Time Operations
55409RESERVE NOTICE18/10/2016 10:31:59 AM

Cancellation of the Actual (LOR2) condition in the South Australia region - 18 October 2016

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Actual (LOR2) condition in the South Australia region- 18 October 2016

Refer to AEMO Electricity Market Notice No. 55407

The Actual LOR2 condition in the South Australia Region is cancelled at 1030 hrs 18 October 2016

Manager NEM Real Time Operations
55407RESERVE NOTICE18/10/2016 08:48:37 AM

Actual LOR2 South Australia Region - 18 October 2016

AEMO ELECTRICITY MARKET NOTICE

Actual LOR2 South Australia Region - 18 October 2016
Refer AEMO Electricity Market Notice 55389
An actual LOR2 condition has been declared for the South Australia region from 0840 hrs and is forecast to continue until further notice during a planned outage of Heywood to South East No.2 275 kV transmission line between the Victoria and South Australia regions.

If a credible contingency event occurs in this period the South Australia region would separate from the rest of the NEM and is likely to result in interruptions to power supplies.

There are sufficient capacity reserves in the South Australia region to meet electricity demand but it may not be possible to bring the required additional capacity into service in time to avoid automatic under-frequency load shedding causing power interruptions.

Manager NEM Real Time Operations
55345MARKET INTERVENTION11/10/2016 07:31:20 PM

Cancellation - Direction - South Australia region 11/10/16

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Direction - South Australia region 11/10/16

Refer AEMO Electricity Market Notice 55339

The direction to a participant in the South Australia region was cancelled at 1906 hrs 11/10/16

Manager NEM Real Time Operations
55339MARKET INTERVENTION11/10/2016 05:05:04 PM

Direction - South Australia region 11/10/16

AEMO ELECTRICITY MARKET NOTICE.

Direction - South Australia region 11/10/16

In accordance with clause 4.8.9 of the National Electricity Rules AEMO has issued a direction to a participant in the South Australia region.

The direction was necessary to maintain the power system in a secure operating state.

The direction was issued at 1616 hrs 11/10/16 and is expected to stay in place until 0700 hrs 12/10/16.

Manager NEM Real Time Operations
55337MARKET INTERVENTION11/10/2016 04:12:03 PM

Forecast Intervention Event - South Australia region 11 and 12 October 2016

AEMO ELECTRICITY MARKET NOTICE

Forecast Intervention Event - South Australia region 11 and 12 October 2016

Predispatch is indicating a power system security violation in the South Australia region between 2100 hrs 11/10/16 and 1400hrs 12/10/16.

AEMO is seeking a market response from synchronous generating units in the South Australia region with an installed capacity of greater than 100 MW.

AEMO will determine the latest time at which it would need to intervene through a AEMO intervention event.

Manager NEM Real Time Operations
55334MARKET INTERVENTION11/10/2016 01:05:05 PM

Forecast Intervention Event - South Australia region 12/10/16

AEMO ELECTRICITY MARKET NOTICE

Forecast Intervention Event - South Australia region 12/10/16

Predispatch is indicating a power system security violation in the South Australia region between 0000 hrs and 1400hrs Wednesday 12 October 2016.

AEMO is seeking a market response from synchronous generating units in the South Australia region with an installed capacity of greater than 100 MW.

AEMO will determine the latest time at which it would need to intervene through a AEMO intervention event.

Manager NEM Real Time Operations
55308MARKET INTERVENTION10/10/2016 05:32:49 AM

Cancellation - Direction - South Australia region

Cancellation - Direction - South Australia region

Refer AEMO Electricity Market Notice 55293

The direction was issued at 2054 hrs 09/10/16 and cancelled at 0530 hrs 10/10/16.

Manager NEM Real Time Operations
55294MARKET INTERVENTION09/10/2016 10:04:11 PM

Direction - South Australia region - Intervention Pricing

AEMO ELECTRICITY MARKET NOTICE.

Refer AEMO Electricity Market Notice no. 55293.

An AEMO Intervention Event has been implemented by issuing a direction to maintain the power system in a secure operating state.

AEMO declares all dispatch intervals during the AEMO Intervention Event to be intervention price dispatch intervals.

The AEMO Intervention Event will commence in the 0000 hrs 10/10/16 dispatch interval and is forecast to apply until 0530 hrs 10/10/16

Intervention pricing will not be implemented from the 0000 hrs 10/10/16 dispatch interval until the end of the AEMO Intervention Event.

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm