Forecast Lack of Reserve Level 2 (LOR2) in the SA region - PDPASA - 07 July 2016
Forecast Lack of Reserve Level 2 (LOR2) in the SA region - PDPASA - 07 July 2016
AEMO declares a Forecast LOR2 condition for the SA region.
From 1830 hrs to 1930 hrs 07 July 2016
The contingency capacity reserve required is 220 MW
The minimum reserve available is 198 MW
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of the Forecast (LOR2) condition in the South Australia Region - STPASA
Cancellation of the Forecast (LOR2) condition in the SA Region - STPASA - 07/07/2016
The Forecast LOR2 condition in the SA Region advised in AEMO Electricity Market Notice No 54191 is cancelled at 1015 hrs 02/07/2016.
Manager NEM Real Time Operations
FORECAST LACK OF RESERVE LEVEL 2 (LOR2) in the South Australia region (ST PASA).
FORECAST LACK OF RESERVE LEVEL 2 (LOR2) in the South Australia region (ST PASA).
AEMO declares a forecast LOR2 condition for the South Australia region for the following period.
Thursday 7th July 2016 from 1830 hrs to 1900 hrs
The minimum reserve available is 196 MW.
This calculation is based on a LOR2 trigger level of 200 MW.
AEMO is seeking a market response.
Manager NEM Real Time Operations
Cancellation of the Forecast (LOR2) condition in the SA Region - STPASA - 04/07/2016
Cancellation of the Forecast (LOR2) condition in the SA Region - STPASA - 04/07/2016
The Forecast LOR2 condition in the SA Region advised in AEMO Electricity Market Notice No54176 is cancelled at 2200 hrs 29/06/2016.
Manager NEM Real Time Operations
Update: Forecast Lack Of Reserve Level 2 (LOR2) in the South Australia region - STPASA - 04/07/2016
RE: AEMO Electricity Market Notice No. 54172 & 54173.
NOTICE OF UPDATE
AEMO declares forecast LOR2 conditions for the South Australia region for the following period:
From 04/07/2016 1800 hrs to 2000 hrs
The contingency capacity reserve required is 200 MW
The minimum reserve available is 136 MW
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Harmohan Singh
Operations Planning
Update: Forecast Lack Of Reserve Level 2 (LOR2) in the South Australia region - STPASA - 04/07/2016
RE: AEMO Electricity Market Notice No. 54157 & 54160.
NOTICE OF UPDATE
AEMO declares forecast LOR2 conditions for the South Australia region for the following period:
From 04/07/2016 1830 hrs to 1930 hrs
The contingency capacity reserve required is 200 MW
The minimum reserve available is 166 MW
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Harmohan Singh
Operations Planning
Update: Forecast Lack Of Reserve Level 2 (LOR2) in the South Australia region - STPASA - 04/07/2016
RE: AEMO Electricity Market Notice No. 54157.
NOTICE OF UPDATE
AEMO declares forecast LOR2 conditions for the South Australia region for the following periods:
From 04/07/2016 1800 hrs to 2000 hrs
The contingency capacity reserve required is 200 MW
The minimum reserve available is 110 MW
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Harmohan Singh
Operations Planning
Forecast Lack Of Reserve Level 2 (LOR2) in the South Australia region - STPASA - 04/07/2016
AEMO declares a Forecast LOR2 condition for the South Australia region for the following period:
From 04/07/2016 1800 hrs to 1900 hrs
The contingency capacity reserve required is 200 MW
The minimum reserve available is 165 MW
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Operations Planning
[EventId:201605190100_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 19 May 2016 01:00
Issued by Australian Energy Market Operator Ltd at 0100 hrs on 19 May 2016
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 19 May 2016.
Refer to market notice: 53406
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 0100 hrs on 19 May 2016.
This is an AEMO autogenerated Market Notice.