75176PRICES SUBJECT TO REVIEW04/04/2020 04:45:18 PM

[EventId:202004041650_review] Prices for interval 04-Apr-2020 16:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1645 hrs on 4 April 2020

PRICES ARE SUBJECT TO REVIEW for dispatch interval 04-Apr-2020 16:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
75175PRICES SUBJECT TO REVIEW04/04/2020 04:40:41 PM

[EventId:202004041645_review] Prices for interval 04-Apr-2020 16:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1640 hrs on 4 April 2020

PRICES ARE SUBJECT TO REVIEW for dispatch interval 04-Apr-2020 16:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
75174RECLASSIFY CONTINGENCY04/04/2020 04:39:40 PM

Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Duration: 04/04/2020 16:39 until further notice

Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
75173RECLASSIFY CONTINGENCY04/04/2020 04:39:40 PM

Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Duration: 04/04/2020 16:39 until further notice

Constraint set(s) invoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
75172PRICES SUBJECT TO REVIEW04/04/2020 04:35:12 PM

[EventId:202004041640_review] Prices for interval 04-Apr-2020 16:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1635 hrs on 4 April 2020

PRICES ARE SUBJECT TO REVIEW for dispatch interval 04-Apr-2020 16:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
75171RECLASSIFY CONTINGENCY04/04/2020 04:18:55 PM

Cancellation of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Cancellation time: 04/04/2020 16:18

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 75166

Auto-generated on behalf of Manager NEM Real Time Operations
75170RECLASSIFY CONTINGENCY04/04/2020 03:58:55 PM

Cancellation of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Cancellation time: 04/04/2020 15:58

Constraint set(s) revoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
VIC1-NSW1


Refer AEMO Electricity Market Notice 75157

Auto-generated on behalf of Manager NEM Real Time Operations
75169RECLASSIFY CONTINGENCY04/04/2020 03:38:10 PM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 04/04/2020 15:38 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
75168MARKET INTERVENTION04/04/2020 03:30:21 PM

Cancellation - AEMO Intervention Event - Intervention dispatch intervals - Direction SA region - 3/04/2020

AEMO ELECTRICITY MARKET NOTICE

Refer Market Notice 75106

The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs 4/04/2020.

Manager NEM Real Time Operation