Forecast Lack Of Reserve Level 3 (LOR3) in the Vic Region - STPASA
Forecast Lack Of Reserve Level 3 (LOR3) in the Vic Region - STPASA
Under the NER Cl 4.8.4(d), AEMO considers that Customer load would be interrupted in order to maintain or restore the security of the power system in Vic Region, for the following period,
AEMO declares a Forecast LOR3 condition for the Vic Region.
From 1730 hrs to 1800 hrs 11/05/2017
The maximum load forecast to be interrupted is 37 MW at 1730 hrs 11/05/2017
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through a AEMO intervention event.
Manager NEM Real Time Operations
Cancellation - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Cancellation - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Refer to AEMO Electricity Market Notice 57339, 57357
AEMO has cancelled the forecast LOR3 condition for the NSW Region for the following period as previously advised.
Friday 10th February 2017 from 1600 hrs to 1700 hrs
Manager NEM Real Time Operations
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Refer to AEMO Electricity Market Notice 57339, 57357
AEMO declares forecast LOR3 condition for the NSW Region for the following period.
Friday 10th February 2017 from 1600 hrs to 1700 hrs
The minimum reserve available is -189
This calculation is based on a LOR3 trigger level of 0 MW.
AEMO is seeking a market response.
AEMO will intervene through an AEMO intervention event as required in the dispatch timeframe.
Manager NEM Real Time Operations
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Refer to AEMO Electricity Market Notice 57339
AEMO declares forecast LOR3 condition for the NSW Region for the following period.
Friday 10th February 2017 from 1600 hrs to 1700 hrs
The minimum reserve available is -77
This calculation is based on a LOR3 trigger level of 0 MW.
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
AEMO declares forecast LOR3 condition for the NSW Region for the following period.
Friday 10th February 2017 from 1500 hrs to 1730 hrs
The minimum reserve available is --419 MW.
This calculation is based on a LOR3 trigger level of 0 MW.
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
AEMO declares forecast LOR3 condition for the NSW Region for the following period.
Friday 10th February 2017 from 1500 hrs to 1700 hrs
The minimum reserve available is --264 MW.
This calculation is based on a LOR3 trigger level of 0 MW.
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- ST PASA.
FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- ST PASA.
AEMO declares forecast LOR3 condition for the NSW Region for the following period.
Friday 10th February 2017 from 1600 hrs to 1630 hrs
The minimum reserve available is -19 MW.
This calculation is based on a LOR3 trigger level of 0 MW.
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Change to FCAS Regulation constraint equations for managing time error
Change to FCAS Regulation constraint equations for managing time error
AEMO is changing the way the FCAS constraint equations work for automatically increasing the regulation when the time error exceeds 1.5s in the Mainland. Currently the regulation is required from all NEM regions when there is a Mainland (NSW, Qld, SA and Victoria) time error.
The change to be made is to set the FCAS regulation requirements for Mainland regions only when there is a Mainland time error exceedance.
The FCAS requirements from all NEM regions of 120 MW lower regulation and 130 MW raise regulation has not changed.
The calculation for the regulation is detailed in SO_OP3715, section 19.
This change will take effect at 1700 hrs on 25 October 2016.
Ben Blake
AEMO Operations
Updates to Victorian system normal stability constraint equations
The Victorian system normal constraint equations that determine Victorian export limits based on transient stability and voltage stability at Heywood for Victoria to South Australia flows will be updated to a revised formulation on 25 July 2016 after 1330 hrs. This revised formulation models the effects of higher flows on Victoria to SA on Heywood and the new series capacitors at Black Range.
The changes are to the following constraint equations :
V::N_NIL_V1
V::N_NIL_V2
V::N_NIL_Q1
V::N_NIL_Q2
V::N_NIL_S1
V::N_NIL_S2
V::N_NIL_SD
V^S_HYCP
Ben Blake
AEMO Operations