Variation to FCAS Lower regulation requirements for Mainland Regulation - 4 Oct 2016
Variation to FCAS Lower regulation requirements for Mainland Regulation 04/10/2016.
The FCAS Lower regulation requirement was increased to manage time error to within standards.
The following constraint was invoked to increase the lower regulation requirements being dispatched in Vic, NSW and QLD.
#LR_20161004084741 invoked from 0850 hrs.
Manager NEM Real Time Operations
Cancellation - Variation to FCAS regulation requirements: NEM Global for Mainland Regulation - 3 Oct 2016
Cancellation - Variation to FCAS regulation requirements: NEM Global for Mainland Regulation 03/10/2016.
Normal FCAS Lower regulation requirements applied to manage time error to within standards.
The following constraint was revoked to manage lower regulation requirements.
F-MAIN_LREG_400 revoked from 2215 hrs.
Manager NEM Real Time Operations
Variation to FCAS regulation requirements: NEM Global for Mainland Regulation - 3 Oct 2016
Variation to FCAS regulation requirements: NEM Global for Mainland Regulation 03/10/2016.
FCAS Lower regulation requirements was increased to manage time error to within standards.
The following constraint was invoked to manage lower regulation requirements.
F-MAIN_LREG_400 invoked from 2135 hrs.
Manager NEM Real Time Operations
Cancellation - Variation to FCAS regulation requirements: NEM Global for Mainland Regulation - 3 Oct 2016
Cancellation - Variation to FCAS regulation requirements: NEM Global for Mainland Regulation 30/09/2016.
Normal FCAS Lower regulation requirements applied to manage time error to within standards.
The following constraint was revoked to manage lower regulation requirements.
F-MAIN_LREG_400 revoked from 0150 hrs.
Manager NEM Real Time Operations
Variation to FCAS regulation requirements: NEM Global for Mainland Regulation - 3 Oct 2016
Variation to FCAS regulation requirements: NEM Global for Mainland Regulation 30/09/2016.
FCAS Lower regulation requirements was increased to manage time error to within standards.
The following constraint was invoked to manage lower regulation requirements.
F-MAIN_LREG_400 invoked from 0120 hrs.
Manager NEM Real Time Operations
Cancelled Lower Regulation FCAS Increase 30/09/16
Cancellled the variation to FCAS regulation requirements: NEM Global for Mainland Regulation 30/09/2016.
As the time error has returned to an acceptable level, the following constraint was revoked
F-MAIN_LREG_400 revoked from 2210 hrs.
Manager NEM Real Time Operations
Lower Regulation FCAS Increased -30/09/16
Variation to FCAS regulation requirements: NEM Global for Mainland Regulation 30/09/2016.
FCAS Lower regulation requirements was increased to manage time error to within standards.
The following constraint was invoked to manage lower regulation requirements.
F-MAIN_LREG_400 invoked from 2135 hrs.
Manager NEM Real Time Operations
Cancellation of the planned outages in Victoria region from 05/10/2016 to 07/10/2016
Cancellation of following planned outages in Victoria region from 05/10/2016 to 07/10/2016:
- The Moorabool to Tarrone 500 kV line. Refer to AEMO Electricity Market Notice 54936.
- The Heywood to Tarrone 500 kV line. Refer to AEMO Electricity Market Notice 54859.
- The Heywood No.1 500 kV busbar. Refer to AEMO Electricity Market Notice 54850.
AEMO Operations
Cancelled Lower Regulation FCAS Increase 29/09/16
Cancellled the variation to FCAS regulation requirements: NEM Global for Mainland Regulation 29/09/2016.
As the time error has returned to an acceptable level, the following constraint was revoked
F-MAIN_LREG_400 revoked from 0300 hrs.
Manager NEM Real Time Operations