Market Notices

54171GENERAL NOTICE29/06/2016 02:55:03 PM

Planned outage of Tailem Bend 275kV - South East 275kV No.1 line from 04/07/2016 0745 hrs to 12/07/2016 1730hrs

AEMO ELECTRICITY MARKET NOTICE.

Planned outage of Tailem Bend 275kV - South East 275kV No.1 line from 04/07/2016 0745 hrs to 12/07/2016 1730hrs

During these outage, South Australia region will remain connected to the NEM. However, there is a risk of South Australia region separating from the rest of the NEM following the next credible contingency (trip Tailem Bend 275kV - South East 275kV No.2 line).

AEMO will take all necessary steps as outlined in Section 6.1 of SO-OP-3715 Power System Security Guideline to manage the orderly separation of SA from the NEM following the next credible contingency.

Prior to the orderly separation of SA, the following FCAS regulation constraints will be invoked to manage security of South Australia power system.

F-S_LREG_0035
F-S_RREG_0035

Refer to AEMO Network Outage Schedule (NOS) for further details


Operations Planning
54170GENERAL NOTICE29/06/2016 02:59:12 AM

Network Augmentation Commissioned - Vic Region 29 June 2016

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned in the Victoria Region

The Ararat Terminal Station (ARTS) was commissioned at 0203 hrs 29 June 2016. The ARTS substation has been cut into the former Horsham - Waubra 220kV Line to form two new transmission lines namely, Ararat - Horsham 220kV Line and Ararat - Waubra 220kV Line

Manager NEM Real Time Operations
54164GENERAL NOTICE28/06/2016 05:45:55 PM

Update - Raise Regulation FCAS Increased - 28/06/16

AEMO ELECTRICITY MARKET NOTICE

Update - Variation to FCAS regulation requirements: NEM Global - 28/06/16.

FCAS Raise regulation requirements were increased to manage time error to within standards.

The following constraints wasinvoked to manage raise regulation requirements.

F-MAIN_RREG_0400 invoked from 1715 hrs to 1745 hrs

Manager NEM Real Time Operations
54163GENERAL NOTICE28/06/2016 05:11:12 PM

Update - Raise Regulation FCAS Increased - 28/06/16

AEMO ELECTRICITY MARKET NOTICE

Update - Variation to FCAS regulation requirements: NEM Global - 28/06/16.

FCAS Raise regulation requirements have been increased to manage time error to within standards.

The following constraints have been invoked to manage raise regulation requirements.

F-MAIN_RREG_0400invoked from 1715 hrs until further notice.

Manager NEM Real Time Operations
54162INTER-REGIONAL TRANSFER28/06/2016 05:14:30 PM

Update on Heywood Interconnector upgrade

AEMO ELECTRICITY MARKET NOTICE

Update on Heywood Interconnector upgrade

Refer to Market Notice 51916

ElectraNet expects to achieve commercial operation of the South East - Tailem Bend 275 kV line series compensation by 31 July 2016. At this time, capability of the Heywood interconnector will be 570 MW for transfer from Victoria to South Australia and 500 MW for transfer from South Australia to Victoria. Further transfer capability will be released subject to completion of inter-network testing to prove system performance and validate system models. System conditions for the conduct of these tests are being obtained through normal market dispatch.

Based on progress with the testing to date, full capability for transfer from Victoria to South Australia is likely to be achieved by February 2017. However, it appears unlikely that the market will deliver sufficient test conditions to enable achievement of full capability for transfer from South Australia to Victoria before March 2017.
If the full range of required conditions are not obtained by July 2017, AEMO and ElectraNet may seek to obtain test facilitation services in order to complete the inter-network tests. This will allow the market approximately 12 months to deliver the required test conditions from when the South East - Tailem Bend series compensation is commissioned.

The inter-network test program for the Heywood interconnector upgrade provides further information and is published on AEMO's website at the following link:
http://www.aemo.com.au/Consultations/National-Electricity-Market/Heywood-interconnector-upgrade-program-for-internetwork-tests

AEMO Operations
54161GENERAL NOTICE28/06/2016 04:32:57 PM

Raise Regulation FCAS Increased - 28/06/16

AEMO ELECTRICITY MARKET NOTICE

Variation to FCAS regulation requirements: NEM Global - 28/06/16.

FCAS Raise regulation requirements have been increased to manage time error to within standards.

The following constraints have been invoked to manage raise regulation requirements.

F-MAIN_RREG_0350 invoked from 1630 hrs until further notice.

Manager NEM Real Time Operations
54152GENERAL NOTICE27/06/2016 05:32:51 PM

Update - Raise Regulation FCAS Increased - 27/06/16

AEMO ELECTRICITY MARKET NOTICE

Update - Variation to FCAS regulation requirements: NEM Global - 27/06/16.

Refer to MN 54151

FCAS Raise regulation requirements were increased to manage time error to within standards.

The following constraints were invoked to manage raise regulation requirements.

F-MAIN_RREG_0350 invoked from 1650 hrs to 1735 hrs

Manager NEM Real Time Operations
54151GENERAL NOTICE27/06/2016 04:55:35 PM

Raise Regulation FCAS Increased - 27/06/16

AEMO ELECTRICITY MARKET NOTICE

Variation to FCAS regulation requirements: NEM Global - 27/06/16.

FCAS Raise regulation requirements have been increased to manage time error to within standards.

The following constraints have been invoked to manage raise regulation requirements.

F-MAIN_RREG_0350 invoked from 1650 hrs until further notice.

Manager NEM Real Time Operations
54140INTER-REGIONAL TRANSFER26/06/2016 06:05:06 AM

Inter-regional transfer limit variation - Horsham-Waubra 220 kV Transmission Line (Vic)

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Horsham-Waubra 220 kV Transmission Line (Vic)

The planned outage of the Horsham-Waubra 220 kV Line starting at 0600 hrs has been cancelled.

The following constraint set was associated with this outage.
V-HOWA

The constraint set contains equations with the following interconnectors on the LHS.

NSW-QLD1
VIC1-NSW1
V-SA
V-S-MNSP1
T-V-MNSP1

Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm