Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 04/01/2021 11:26 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Condabri Nth - Condabri Central 7400 132kV line and Condabri Nth - Condabri Central 7401 132kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Condabri Nth - Condabri Central 7400 132kV and Condabri Nth - Condabri Central 7401 132kV
Duration: 04/01/2021 10:46 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Condabri Nth - Condabri Central 7400 132kV line and Condabri Nth - Condabri Central 7401 132kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Condabri Nth - Condabri Central 7400 132kV and Condabri Nth - Condabri Central 7401 132kV
Cancellation time: 04/01/2021 09:19
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 81864
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Monday, 4 January 2021
NON-CONFORMANCE QLD1 Region Monday, 4 January 2021
AEMO declared a schedule generating unit non-conforming
Unit: TNPS1
Duration: 04/01/2021 09:00 to 04/01/2021 09:10
Amount: -20 MW
Constraint: NC-Q_TNPS1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV
Cancellation time: 04/01/2021 08:59
Constraint set(s) revoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1
Refer AEMO Electricity Market Notice 81863
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Tarong - Chinchilla No.7168 132 kV line and Tarong - Chinchilla No.7183 132 kV line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Tarong - Chinchilla No.7168 132 kV and Tarong - Chinchilla No.7183 132 kV
Cancellation time: 04/01/2021 08:59
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 81862
Auto-generated on behalf of Manager NEM Real Time Operations
Planned outage of Moorabool - Mortlake 500 kV line in the Victoria region from 30 January to 6 February 2021
The Moorabool - Mortlake 500 kV line in the Victoria (VIC) region is planned to be out of service from 30 January 0500hrs to 6 February 2021 1730 hrs.
A credible contingency event during this planned outage could cause synchronous separation of the South Australia (SA) region from the rest of the NEM. If separation occurs, load may be interrupted due to the operation of the Automatic Under Frequency Load Shedding (AUFLS) scheme in SA.
The credible separation contingency is managed as follows:
- When power transfer is from SA to Victoria, contingency lower FCAS will be sourced from SA.
- When power transfer is from Victoria to SA, due to the 47-52Hz island separation frequency band advised by the SA jurisdiction, contingency raise FCAS is not sourced in SA and the AUFLS scheme may respond to low frequency events.
- Power transfer will be restricted on Victoria - South Australia interconnector (Heywood interconnector) to manage system security following the loss of the next contingency.
Forecast capacity reserves in the SA region are currently sufficient to meet electricity demand during the planned outage.
The following constraint sets have been invoked for this outage:
S-X_BC_CP
V-MLMO
Refer to AEMO Network Outage Schedule (NOS) for further details.
Diyoni Hoole
AEMO Operations
Reclassification of a Non-Credible Contingency Event: Condabri Nth - Condabri Central 7400 132kV line and Condabri Nth - Condabri Central 7401 132kV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Condabri Nth - Condabri Central 7400 132kV and Condabri Nth - Condabri Central 7401 132kV
Duration: 04/01/2021 06:17 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: QLD1
Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV
Duration: 04/01/2021 05:55 until further notice
Constraint set(s) invoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations