Market Notices

53358RECLASSIFY CONTINGENCY17/05/2016 03:00:07 AM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.

Refer AEMO Electricity Market Notice 53335

There is no longer any lightning activity in the vicinity of the Rowville - Yallourn No.5 & No.6 220 kV Lines.

AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0300 hrs.

Constraint Set

V-ROYP56_R_N-2 revoked.


Manager NEM Real Time Operations
53357PRICES UNCHANGED17/05/2016 02:17:10 AM

[EventId:201605170220_confirmed] Prices for interval 17-May-2016 02:20 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0217 hrs on 17 May 2016

PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 02:20.

In accordance with Market Notice 53356 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
53355PRICES UNCHANGED17/05/2016 02:12:04 AM

[EventId:201605170215_confirmed] Prices for interval 17-May-2016 02:15 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0212 hrs on 17 May 2016

PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 02:15.

In accordance with Market Notice 53354 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
53353PRICES UNCHANGED17/05/2016 01:43:02 AM

[EventId:201605170145_confirmed] Prices for interval 17-May-2016 01:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0142 hrs on 17 May 2016

PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 01:45.

In accordance with Market Notice 53352 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
53351PRICES UNCHANGED17/05/2016 01:38:00 AM

[EventId:201605170140_confirmed] Prices for interval 17-May-2016 01:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0137 hrs on 17 May 2016

PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 01:40.

In accordance with Market Notice 53350 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
53349PRICES UNCHANGED17/05/2016 12:47:03 AM

[EventId:201605170050_confirmed] Prices for interval 17-May-2016 00:50 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0047 hrs on 17 May 2016

PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 00:50.

In accordance with Market Notice 53348 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
53347PRICES UNCHANGED17/05/2016 12:42:31 AM

[EventId:201605170045_confirmed] Prices for interval 17-May-2016 00:45 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0042 hrs on 17 May 2016

PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 00:45.

In accordance with Market Notice 53345 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
53346PRICES UNCHANGED17/05/2016 12:42:13 AM

[EventId:201605170040_confirmed] Prices for interval 17-May-2016 00:40 are now confirmed

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 0042 hrs on 17 May 2016

PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 00:40.

In accordance with Market Notice 53344 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply

Prices remain unchanged.


This is an AEMO autogenerated Market Notice.
53343RECLASSIFY CONTINGENCY17/05/2016 12:34:21 AM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.

Lightning is occurring near the Farrell- Reece No. 1 and No. 2 220 kV Lines.

AEMO considers the simultaneous trip of those circuits to now be more likely.

Therefore AEMO has reclassified this as a credible contingency event from 0035hrs 17 May 2016 until further notice.

Constraint Set F-T-FARE_N-2 invoked.


Manager NEM Real Time Operations