Cancellation of the Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No.5 & No.6 220 kV Lines in Victoria due to Lightning.
Refer AEMO Electricity Market Notice 53335
There is no longer any lightning activity in the vicinity of the Rowville - Yallourn No.5 & No.6 220 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0300 hrs.
Constraint Set
V-ROYP56_R_N-2 revoked.
Manager NEM Real Time Operations
[EventId:201605170220_confirmed] Prices for interval 17-May-2016 02:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0217 hrs on 17 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 02:20.
In accordance with Market Notice 53356 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:201605170215_confirmed] Prices for interval 17-May-2016 02:15 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0212 hrs on 17 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 02:15.
In accordance with Market Notice 53354 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:201605170145_confirmed] Prices for interval 17-May-2016 01:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0142 hrs on 17 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 01:45.
In accordance with Market Notice 53352 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:201605170140_confirmed] Prices for interval 17-May-2016 01:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0137 hrs on 17 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 01:40.
In accordance with Market Notice 53350 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:201605170050_confirmed] Prices for interval 17-May-2016 00:50 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0047 hrs on 17 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 00:50.
In accordance with Market Notice 53348 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:201605170045_confirmed] Prices for interval 17-May-2016 00:45 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0042 hrs on 17 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 00:45.
In accordance with Market Notice 53345 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
[EventId:201605170040_confirmed] Prices for interval 17-May-2016 00:40 are now confirmed
Issued by Australian Energy Market Operator Ltd at 0042 hrs on 17 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 17-May-2016 00:40.
In accordance with Market Notice 53344 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
Prices remain unchanged.
This is an AEMO autogenerated Market Notice.
Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Reclassification of a Non-Credible Contingency Event: Farrell - Reece No. 1 and No. 2 220 kV Lines in Tasmania due to Lightning.
Lightning is occurring near the Farrell- Reece No. 1 and No. 2 220 kV Lines.
AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 0035hrs 17 May 2016 until further notice.
Constraint Set F-T-FARE_N-2 invoked.
Manager NEM Real Time Operations