Updates to Victorian system normal stability constraint equations
The Victorian system normal constraint equations that determine Victorian export limits based on transient stability and voltage stability at Heywood for Victoria to South Australia flows will be updated to a revised formulation on 25 July 2016 after 1330 hrs. This revised formulation models the effects of higher flows on Victoria to SA on Heywood and the new series capacitors at Black Range.
The changes are to the following constraint equations :
V::N_NIL_V1
V::N_NIL_V2
V::N_NIL_Q1
V::N_NIL_Q2
V::N_NIL_S1
V::N_NIL_S2
V::N_NIL_SD
V^S_HYCP
Ben Blake
AEMO Operations
Planned System Maintenance - Electricity MMS Production Site Transfer (From QLD to NSW)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Planned System Maintenance - Electricity MMS Production Site Transfer (From QLD to NSW)
Change Start Date & Time: 26/07/2016 13:00:00 AEST
Change End Date & Time: 26/07/2016 14:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Change Description:
The EMMS Production System is to be transferred to the alternate site to support EMMS maintenance activities.
Environment: Production
Participant Impact and Requirements:
The transfer is not expected to have any impact, however there may be disconnections to the AEMO Web Portal. Participants are reminded that this activity is not without risk and therefore if an electricity market system issue is identified after the transfer it should be reported to AEMO.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Planned System Maintenance - Gas Supply Hub Production Site Transfer
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: Planned System Maintenance - Gas Supply Hub Production Site Transfer
Change Start Date & Time: 26/07/2016 19:00:00 AEST
Change End Date & Time: 26/07/2016 21:00:00 AEST
Outage Start Date & Time: 26/07/2016 19:00:00 AEST
Outage End Date & Time: 26/07/2016 20:00:00 AEST
Change Description:
The Gas Supply Hub Production System is to be transferred to the alternate site to support maintenance activities (QLD to NSW)
Environment: Production
Participant Impact and Requirements:
All access to the Gas Supply Hub (Exchange Trading System) will be unavailable during the outage period. Please access outside this outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Cancellation of Actual (LOR1) condition in the South Australia region - 14/07/16
Cancellation of Actual (LOR1) condition in the South Australia region - 14/07/16
The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice 54507 is cancelled at 2030 hrs 14/07/16
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. 14/07/16
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. 14/07/16.
An Actual LOR1 condition has been declared for the SA Region from 1745 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs
The contingency capacity reserve required is 440 MW
The minimum reserve available is 342 MW
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the South Australia region - 13/07/16
Cancellation of Actual (LOR1) condition in the South Australia region - 13/07/16
The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice 544785 is cancelled at 2100 hrs 13/07/16
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. 13/07/16
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. 13/07/16.
An Actual LOR1 condition has been declared for the SA Region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 2100 hrs
The contingency capacity reserve required is 400 MW
The minimum reserve available is 281 MW
Manager NEM Real Time Operations
CHG0039788 UPDATE : Planned System Outage due to maintenance on QLD Internet link (Updated Timeline)
Change Number: CHG0039788
Notification issued to: Market Notice
Notification Type: Update
Change Type: Normal
Service/ Component: Wide Area Network
Change Title: Planned System Outage due to maintenance on QLD Internet link (Updated Timeline)
Change Start Date & Time: 20/07/2016 09:00:00 AEST
Change End Date & Time: 20/07/2016 11:00:00 AEST
Outage Start Date & Time: 20/07/2016 09:00:00 AEST
Outage End Date & Time: 20/07/2016 11:00:00 AEST
Change Description:
The AEMO QLD data center internet telecommunications service will experience an outage as part of an upgraded to this service.
Environment: Production
Participant Impact and Requirements:
Impacts and User Requirements
The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - IPWAN Participants - Nil
Lan-2-Lan VPN Participants - Upto 4 x 2 minutes to participants whom have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10)
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.
Remote Access VPN Participants - Upto 4 x 2 minutes to participants who utilise an AEMO RSA token and the AEMO VPN client software to establish their VPN via the AEMO QLD datacenter VPN termination point (202.44.76.8)
Note: Participants are encouraged to establish their VPN client software connections via the alternate AEMO NSW datacenter VPN endpoint (202.44.78.8) prior to this scheduled outage.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0039818: Planned System Outage to the Energy Forecasting Web Portal
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Energy Forecasting Web Portal
Change Title: Planned System Outage to the Energy Forecasting Web Portal
Change Start Date & Time: 15/07/2016 09:00:00 AEST
Change End Date & Time: 15/07/2016 13:00:00 AEST
Outage Start Date & Time: 15/07/2016 09:00:00 AEST
Outage End Date & Time: 15/07/2016 12:00:00 AEST
Change Description:
Update of Forecasting Interactive Website (http://forecasting.aemo.com.au) with usability enhancements and support for previous years forecasts.
Environment: Production
Participant Impact and Requirements:
Forecasting Interactive Website and associated Administration Webpage may not be available during the deployment window. Users need to try accessing the website after the deployment is completed as mentioned in the timeline.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.