CHG0039788 UPDATE : Planned System Outage due to maintenance on QLD Internet link (Updated Timeline)
Change Number: CHG0039788
Notification issued to: Market Notice
Notification Type: Update
Change Type: Normal
Service/ Component: Wide Area Network
Change Title: Planned System Outage due to maintenance on QLD Internet link (Updated Timeline)
Change Start Date & Time: 20/07/2016 09:00:00 AEST
Change End Date & Time: 20/07/2016 11:00:00 AEST
Outage Start Date & Time: 20/07/2016 09:00:00 AEST
Outage End Date & Time: 20/07/2016 11:00:00 AEST
Change Description:
The AEMO QLD data center internet telecommunications service will experience an outage as part of an upgraded to this service.
Environment: Production
Participant Impact and Requirements:
Impacts and User Requirements
The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - IPWAN Participants - Nil
Lan-2-Lan VPN Participants - Upto 4 x 2 minutes to participants whom have established their VPN connection/s via the AEMO QLD datacenter termination point (202.44.76.10)
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO NSW datacenter termination point (202.44.78.10) prior to this scheduled outage.
Remote Access VPN Participants - Upto 4 x 2 minutes to participants who utilise an AEMO RSA token and the AEMO VPN client software to establish their VPN via the AEMO QLD datacenter VPN termination point (202.44.76.8)
Note: Participants are encouraged to establish their VPN client software connections via the alternate AEMO NSW datacenter VPN endpoint (202.44.78.8) prior to this scheduled outage.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0039818: Planned System Outage to the Energy Forecasting Web Portal
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Energy Forecasting Web Portal
Change Title: Planned System Outage to the Energy Forecasting Web Portal
Change Start Date & Time: 15/07/2016 09:00:00 AEST
Change End Date & Time: 15/07/2016 13:00:00 AEST
Outage Start Date & Time: 15/07/2016 09:00:00 AEST
Outage End Date & Time: 15/07/2016 12:00:00 AEST
Change Description:
Update of Forecasting Interactive Website (http://forecasting.aemo.com.au) with usability enhancements and support for previous years forecasts.
Environment: Production
Participant Impact and Requirements:
Forecasting Interactive Website and associated Administration Webpage may not be available during the deployment window. Users need to try accessing the website after the deployment is completed as mentioned in the timeline.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0039787: Planned System Outage - Gas Supply Hub Pre-production
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: Planned System Outage - Gas Supply Hub Pre-production
Change Start Date & Time: 14/07/2016 10:00:00 AEST
Change End Date & Time: 14/07/2016 14:00:00 AEST
Outage Start Date & Time: 14/07/2016 10:00:00 AEST
Outage End Date & Time: 14/07/2016 14:00:00 AEST
Change Description:
Maintenance is performed on Gas Supply Hub periodically to improve security, reliability and performance.
Environment: Pre-Production
Participant Impact and Requirements:
All access to the Preproduction Gas Supply Hub (Exchange Trading System) will be unavailable during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Cancellation of Actual (LOR1) condition in the South Australia region - Tuesday, 12 July 2016
AEMO ELECTRICITY MARKET NOTICE
Cancellation of Actual (LOR1) condition in the South Australia region - Tuesday, 12 July 2016
The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice No 54458 is cancelled at 1930 hrs Tuesday, 12 July 2016.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. Tuesday, 12 July 2016.
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. Tuesday, 12 July 2016.
An Actual LOR1 condition has been declared for the South Australia Region.
From 1830 hrs to 1930 hrs Tuesday, 12 July 2016
The contingency capacity reserve required is 400 MW
The minimum reserve available is 224 MW
Manager NEM Real Time Operations
Cancellation of the Actual (LOR1) condition in the SA region - 8/07/2016
Cancellation of Actual (LOR1) condition in the SA region - 8/07/2016
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.54371 is cancelled at 2000 hrs 8/07/2016.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA Region - 08 July 2016
Actual Lack Of Reserve Level 1 (LOR1) in the SA Region - 08 July 2016
Update to Market Notice 54370
An Actual LOR1 condition has been declared for the SA Region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The contingency capacity reserve required is 400 MW
The reserve available is 343 MW
Manager NEM Real Time Operations
Cancellation of the Actual (LOR1) condition in the SA region - 7/07/2016
Cancellation of Actual (LOR1) condition in the SA region - 7/07/2016
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.54306 is cancelled at 2130 hrs 7/07/2016.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA Region - 07 July 2016
Actual Lack Of Reserve Level 1 (LOR1) in the SA Region - 07 July 2016
An Actual LOR1 condition has been declared for the SA Region from 1815 hrs.
The Actual LOR1 condition is forecast to exist until 2130 hrs
The contingency capacity reserve required is 400 MW
The reserve available is 277 MW
Manager NEM Real Time Operations