Filter by category
Filter by Date
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - 20 May 2016
Refer Market Notice 53435
The Tarong to South Pine (832) 275kV Line has been returned to service.
The following constraint set was revoked at 0535 hrs..
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Cancellation - Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8849) 275kV Line (Qld) - Voltage Control
Cancellation - Inter-regional transfer limit variation - Greenbank to Middle Ridge (8849) 275kV Line (Qld) - Voltage Control - Monday, 16 May 2016
Refer to Market Notice 53437
The Greenbank to Middle Ridge (8849) 275kV Line was returned to service.
The following constraint set was revoked at 0505 hrs.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8849) 275kV Line (Qld) - Voltage Control
Inter-regional transfer limit variation - Greenbank to Middle Ridge (8849) 275kV Line (Qld) - Voltage Control - 20 May 2016
The Greenbank to Middle Ridge (8849) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0225 hrs until further notice.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation for Transient Stability Limit - Vic Region - 20 May 2016
Inter-regional transfer limit variation for Transient Stability Limit - Vic Region - 20 May 2016
The AEMO Dynamic Stability Analysis application is indicating violations for a fault on a Hazelwood - South Morang 500 kV transmission line in the Victoria region.
The following constraints have been invoked to apply offset reductions to the Victoria transient stability export limit.
Constraint V-DSA_STAB-050 invoked from 0215 hrs until further notice
Constraints have the following interconnectors on the LHS
NSW1-QLD1
T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - 20 May 2016
Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - 20 May 2016
The Tarong to South Pine (832) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0115 hrs until further notice.
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
FCAS Regulation unavailable for Dispatch - 19 May 2016
FCAS Regulation unavailable for Dispatch - 19 May 2016
For the two Dispatch Intervals from1725 and 1730 there was no Raise or Lower regulation FCAS dispatched.
The cause is being investigated by AEMO.
Manager NEM Real Time Operations
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - 18 May 2016
Refer MN 53400
The Tarong to South Pine (832) 275kV Line has been returned to service.
The following constraint set was revoked at 0540 hrs..
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - 18 May 2016
Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - 18 May 2016
The Tarong to South Pine (832) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0310 hrs until further notice.
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer Limit Variation - Directlink - NSW Region 17 May 2016
Inter-Regional Transfer Limit Variation - Directlink - NSW Region - 17 May 2016
The planned outage of the DC2 pole of Directlink was scheduled to complete at 1700 hrs 18/05/16.
The outage has completed early
The following constraint set for this outage was revoked at 1455 hrs.
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side:
N-Q-MNSP1
See AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations