53974GENERAL NOTICE15/06/2016 05:38:09 PM

Network Augmentation Commissioned - South Australia Region - 15 June 2016

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - South Australia Region - 15 June 2016

A network augmentation has been commissioned in the South Australia Region

The Mt Lock 275 kV Sub Station was commissioned at 1630 hrs 15 June 2016. Mt Lock substation has been cut into the former Canowie - Davenport 275 kV Line to form two new transmission lines, Canowie - Mt Lock 275 kV Line and Davenport - Mt Lock 275 kV Line.


Manager NEM Real Time Operations
53964RECLASSIFY CONTINGENCY14/06/2016 11:26:00 AM

Cancellation - Reclassification of the loss of Wagga 132kV B bus, the No2 and the No3 330/132kV transformers in NSW region.

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Reclassification of the loss of Wagga 132 kV B bus, the No 2 and the No 3 330/132 kV transformers in NSW region - 14/06/2016.

Refer to Electricity Market Notice 53874 and 53888

Based on advice from the asset owner the circumstances that existed in relation to the tripping of the Wagga substation 132 kV B bus, the No2 and the No3 330/132 kV transformers have now been addressed

Therefore AEMO no longer considers the simultaneous trip of the Wagga substation 132 kV B bus, the No2 and the No3 330/132 kV transformers to be a credible contingency event from 1055 hrs 14/06/2016 .

Manager NEM Real Time Operations
53959GENERAL NOTICE13/06/2016 12:10:02 PM

Basslink Availability

AEMO ELECTRICITY MARKET NOTICE

Basslink Availability

Basslink restored to full operation at 1151 hrs Monday, 13 June 2016


Manager NEM Real Time Operations
53957RECLASSIFY CONTINGENCY13/06/2016 12:09:39 PM

Update - Reclassification of a Non-Credible Contingency Event in TAS Region

AEMO ELECTRICITY MARKET NOTICE

Update - Reclassification of a Non-Credible Contingency Event in TAS Region:
Trip of any Tasmanian Transmission Line and Basslink Interconnector for Basslink flow in the direction of Victoria to Tasmania

Refer to MN 47360 issued 19/12/2014 and MN 47855 issued 23/01/2015.

Advice provided to AEMO indicates that Basslink is unlikely to trip for 220 kV transmission faults close to George Town. As the George Town to Tamar Valley power station 220 kV lines are very short it is unlikely that Basslink will trip for a fault on these lines.

Based on this advice AEMO has reclassified the loss of any transmission line in Tasmania and Basslink Interconnector to be a credible contingency event for Basslink flow in the direction of Victoria to Tasmania only, except for faults on either of the two George Town to Pacific Aluminium 220 kV transmission lines or the George Town to Tamar Valley power station 220 kV transmission line, from 1151 hrs 13/06/2016 until further notice.

Manager NEM Real Time Operations
53888RECLASSIFY CONTINGENCY11/06/2016 05:15:46 PM

Reclassification of the loss of Wagga 132kV B bus, No2 and No3 transformer as a credible event 11 June 2016

AEMO ELECTRICITY MARKET NOTICE

Refer AEMO ELECTRICITY MARKET NOTICE 53874

At 0950 hrs on 11/06/16, the Wagga substation 132kV B bus, the No2 and the No3 330/132kV transformers tripped.

The cause of this non credible contingency event is not known at this stage.
AEMO is not satisfied that this non credible event is unlikely to re-occur.
AEMO therefore classifies this event as being a credible contingency event.

The No3 330/132kV transformer and the bus were placed on load from 1430hrs, the No2 330/132kV transformer remains de-energised.

Manager NEM Real Time Operations


53746GENERAL NOTICE08/06/2016 03:30:57 PM

Changes to raise FCAS requirements in Tasmania

AEMO ELECTRICITY MARKET NOTICE

Changes to raise FCAS requirements in Tasmania

Refer to AEMO Electricity market notice 51618

The adaptive under-frequency load shedding scheme (AUFLS) was implemented in January 2016 to reduce the contingency raise FCAS requirements in Tasmania. TasNetworks has advised AEMO this scheme was disabled at 1000 hrs 8 June 2016. Tasmanian contingency FCAS requirements now do not use the reduction provided by this scheme.

Ben Blake
AEMO Operations
53660GENERAL NOTICE06/06/2016 08:19:53 PM

Constraint Automation to Manage Power Security in Vic Region.

AEMO ELECTRICITY MARKET NOTICE

Constraint Automation to Manage Power Security in Vic Region, Monday, 06 June 2016.

AEMO network analysis indicated that the trip of the Hazelwood Power station to Hazelwood Terminal station No.2 220 kV line would result in an overload of the Hazelwood Power station to Hazelwood Terminal station A1 500 / 220 kV transformer.

AEMO invoked automated constraint set CA_SPS_4667C455 from 1850 to 1905 hrs to manage power system security.


Manager NEM Real Time Operations
53617RECLASSIFY CONTINGENCY04/06/2016 02:35:54 AM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Bouldercombe - Rockhampton 7108 and Bouldercombe - Egans Hill 7221 132 kV Lines in Queensland due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Reclassification of a Non-Credible Contingency Event: Bouldercombe - Rockhampton 7108 and Bouldercombe - Egans Hill 7221 132 kV Lines in Queensland due to Lightning.

Refer to AEMO Electricity Market Notice no. 53614

There is no longer any Lightning activity in the vicinity of the Bouldercombe - Rockhampton 7108 and Bouldercombe - Egans Hill 7221 132 kV Lines.

AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0235 hrs.



Manager NEM Real Time Operations
53616RECLASSIFY CONTINGENCY04/06/2016 01:51:28 AM

Cancellation of the Reclassification of a Non-Credible Contingency Event: Collinsville North - Mackay Tee Proserpine 7125 and 7126 132 kV Lines in Queensland due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the Reclassification of a Non-Credible Contingency Event: Collinsville North - Mackay Tee Proserpine 7125 and 7126 132 kV Lines in Queensland due to Lightning.

Refer AEMO Electricity Market Notice 53607

There is no longer any lightning activity in the vicinity of the Collinsville North - Mackay Tee Proserpine 7125 and 7126 132 kV Lines.

AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 0150 hrs.