NON-CONFORMANCE Region VIC1 Monday, 23 May 2016
NON-CONFORMANCE VIC1 Region Monday, 23 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: HWPS3
Duration: 23/05/2016 04:20 to 23/05/2016 04:30
Amount: 11 MW
Constraint: NC-V_HWPS3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Sunday, 22 May 2016
NON-CONFORMANCE VIC1 Region Sunday, 22 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS2
Duration: 22/05/2016 08:35 to 22/05/2016 08:40
Amount: 20 MW
Constraint: NC-V_YWPS2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Friday, 20 May 2016
NON-CONFORMANCE VIC1 Region Friday, 20 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS1
Duration: 20/05/2016 09:35 to 20/05/2016 10:05
Amount: 19 MW
Constraint: NC-V_YWPS1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 20 May 2016
NON-CONFORMANCE NSW1 Region Friday, 20 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: MP1
Duration: 20/05/2016 00:20 to 20/05/2016 00:25
Amount: -59 MW
Constraint: NC-N_MP1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Refer AEMO Electricity Market Notice 53432
There is no longer any lightning activity in the vicinity of the Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 2310 hrs.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Lightning is occurring near the Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line.
AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 2210 hrs 19/05/16 until further notice.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Refer AEMO Electricity Market Notice 53427
There is no longer any lightning activity in the vicinity of the Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 1255hrs.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Reclassification of a Non-Credible Contingency Event: Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line in Tasmania due to Lightning.
Lightning is occurring near the Farrell - John Butters 220 kV Line and the Farrell - Rosebery Tee Queenstown - Newton 110 kV Line.
AEMO considers the simultaneous trip of those circuits to now be more likely.
Therefore AEMO has reclassified this as a credible contingency event from 1210 hrs 19 MAY 2016 until further notice.
Manager NEM Real Time Operations
Cancellation of the Reclassification of a Non-Credible Contingency Event: Chapel Street - Liapootah No.1 and No.2 220 kV Lines in Tasmania due to Lightning.
Cancellation of the Reclassification of a Non-Credible Contingency Event: Chapel Street - Liapootah No.1 and No.2 220 kV Lines in Tasmania due to Lightning.
Refer AEMO Electricity Market Notice 53419
There is no longer any lightning activity in the vicinity of the Chapel Street - Liapootah No.1 and No.2 220 kV Lines.
AEMO has cancelled the reclassification of the simultaneous trip of those circuits as a credible contingency event at 1130 hrs.
Constraint Set T-CSLI_N-2 revoked.
Manager NEM Real Time Operations